Muster: workforce, rosters, critical controls, productivity and budgets
2,345 words9 subsections4 tablesPlan version 0.1
On this page9
Source: Brenner pass B6 (planning/brenner/B6_operations_plant_tailings_workforce.md, sub-question B6-SQ4),
building on FSS privacy doctrine, R6 §1.5, R7 and W3 data-residency statutes (E501–E549). Every verdict survived
a refuter-first attempt and a forced third alternative: H6.4b (privacy-by-design pseudonymous crew-level
analytics, hard hours/statutory/competency constraints G-MUST-3/4, covariate-adjusted Bayesian partial pooling
G-MUST-2, and G-MUST-6 anti-Goodhart CCV quality monitoring) and H6.4d (causal DiD / staggered-rollout
intervention attribution + exact LMDI labour variance bridge PO-MUST-3 + denominator-typed local-content
commitments) are adopted over H6.4a (individual surveillance leaderboard + soft fatigue penalties, banned by
G-PUSH-1 and G-MUST-1..5) and H6.4c (unadjusted raw shift-tonnage ratios and raw CCV completion counts,
refuted by geological confounding and Goodhart suppression). The crate is fmine-workforce. Muster covers:
- the people who run the mine, and whether the plan is executable with the crews, competencies and hours available;
- whether critical controls are verified;
- what labour costs and produces, measured honestly.
19.1 Doctrine
- People data is the most sensitive non-MNPI data in the system. Muster follows FSS privacy doctrine:
- purpose limitation and data minimization;
- a lawful basis recorded per data category;
- aggregation by default;
- jurisdiction-specific packs for labour law, works councils and collective agreements;
- residency rules (§31).
- Individual-level performance metrics are off by default. Enabling one requires a recorded lawful basis, a policy attestation and, where applicable, works-council or union consultation evidence (guard G-MUST-1).
- Fatigue and health-adjacent data (fatigue-detection events, fitness-for-work tests, biometric wearables) is a restricted lane with its own access policy. It is never used for discipline through FrankenMining.
- Safety constraints are hard constraints, never priced (G-PUSH-1). Hours-of-work limits, statutory appointments and competency requirements cannot be traded against dollars in any optimization. GB-23 shows why this matters.
19.2 Workforce model
| Object | Content |
|---|---|
Position |
Seat type (haul truck operator, shovel operator, fitter, process technician, shift supervisor, geotechnical engineer…), site, department, coverage requirement (24/7, day only), statutory flag |
Person (pseudonymous ID by default) |
Employment type (employee, contractor, labour hire), home base, residency pattern (FIFO, DIDO, residential), competencies, agreements |
Roster |
Swing pattern (e.g. 14/7, 8/6, 4-panel residential), shift length, day/night rotation, panel assignments, valid time |
Competency |
Training records, licences and tickets (equipment class, blasting licence, confined space, working at heights), statutory certificates, expiry, assessor |
StatutoryAppointment |
Jurisdictional roles (e.g. mine manager, underground manager, quarry manager, ventilation officer, registered EoR where applicable), holder, deputy, valid time |
Agreement |
Enterprise or collective agreement rules: allowances, overtime, minimum rest, maximum consecutive shifts, notice periods. These are rule data, not code. |
Absence |
Planned leave, sick leave, training, travel days. Aggregated by default. |
19.3 Rosters and executability
-
Local content is a commitment with a denominator. An
OB-REVIEWlocal-content commitment declares its denominator scope (owner vs contractor employees), its locality definition and its target. Without a target it renders as "indicator without commitment" (E348). -
Coverage. For each position and period, the roster supplies seats × hours. FTE per seat depends on the swing pattern, shift length and absence rate (GB-23).
-
Feasibility checks (deterministic):
- hours-of-work rules (maximum shift length, minimum rest, maximum consecutive shifts and nights);
- statutory appointments covered at all times, deputies included;
- competency coverage per shift: every seat in the plan has a qualified, unexpired person.
-
Plan executability (link to Pushback, §15.8).
- A tactical plan's equipment hours imply crew hours per competency. A shortfall is a constraint violation surfaced before the plan is published.
- Labour availability is a covariate of schedule compliance.
-
Contractors and campaigns. Shutdown and maintenance campaigns, development contractors and drilling contractors are capacity blocks with their own competencies and rates. Contract terms are documents in the FA Docket (§21).
-
Local employment and community commitments. Local-content percentages and training commitments from community or government agreements are constraints with evidence, tracked as obligations (
OB-REVIEW).
19.4 Fatigue risk
-
Biomathematical scoring. Rosters are scored with a biomathematical fatigue model:
- the three-process model of alertness (Åkerstedt–Folkard) as the open reference implementation;
- vendor models (FAID or SAFTE-class) as
UntrustedCandidatescores where licensed.
Scores are claims with a validity domain: shift-worker populations, not individuals.
-
Fatigue events from detection systems (in-cab camera alerts, collision-avoidance interventions) are restricted evidence. They are aggregated to roster × shift-hour patterns to test whether a roster change reduced events. That test is a registered forecast.
-
Outputs.
- Fatigue-risk distributions by roster and shift block.
- The hours where risk peaks (end of night shifts, first nights after a swap).
- Mitigations (rotation direction, swing length, break scheduling), proposed as roster alternatives on a DecisionCard. Hours limits remain hard constraints.
19.5 Critical control management
FACT[U] (ICMM 2015 Critical Control Management guidance):
- Material unwanted events (MUEs) have critical controls.
- Controls are verified in the field by supervisors (critical control verification, CCV).
- Verification quality matters as much as completion rate.
DESIGN.
- The control registry. Each MUE has its critical controls, performance requirements and verification
questions as registry data. Examples:
- vehicle interaction;
- fall from height;
- ground failure;
- TSF failure;
- fire underground;
- hazardous substances (cyanide);
- energy isolation;
- explosives.
- Evidence state per control instance. Each
ccv_record (verifier, time, location, answers, photos, non-conformances, actions) updates the control's state toverified-current,verified-stale,failedornot_verified. - Never "safe". The output is the control evidence state across the site, not a safety score. Freshness windows are policy per control.
- CCV is already a pay metric, so Muster measures its quality as well as its completion.
- Critical control verifications are 5% of Barrick's annual incentive, with a 75% threshold and 85% maximum (2025 actual 84%). Barrick says it is "continuing to shift toward the use of leading indicators" (FACT, R6 §1.5).
- A completion rate shows that checks were done, not how well. Muster therefore reports verification quality beside completion: answer variance, photo evidence, non-conformances found per verification, and re-verification agreement on a random audit sample.
- "Zero non-conformances found across 300 verifications" is flagged for audit, not celebrated.
- Leading indicators. CCV completion and quality, non-conformance closure times, and high-potential incidents (HPIs). The hypothesis "failed CCV rates predict HPIs" is registered and tested. Muster does not presume it.
- Linkages:
- Incidents (HPIs, injuries, near misses) are recorded with investigation outcomes. Causal factors link to the controls that failed, which makes the MUE → control → evidence → incident graph queryable.
19.6 Productivity, measured honestly
- Driver-based productivity. Productivity is measured per process with its natural driver:
- t/operator-hour (load and haul);
- metres advanced per crew-shift (development);
- metres drilled per rig-hour;
- t milled per plant-hour;
- work orders closed per fitter-hour, by complexity class.
- Confounding is explicit. Productivity depends on geology (hardness, ground conditions), equipment
availability, haul distance and weather as much as on people.
- Hierarchical models with these covariates separate system effects from crew effects.
- Crew-level estimates are shrunk (partial pooling) and shown with intervals.
- Crew rankings without intervals are refused (G-MUST-2).
- Attribution. Productivity changes after an intervention (a new roster, training, autonomy, a new FMS) are
estimated with the counterfactual design registered before the change. Typical designs are
difference-in-differences across comparable pits or a staggered rollout.
- Example: autonomy rollouts at Cortez and Carlin are staggered by site and time (FACT, R6 §1.7), which is a natural experiment if the analysis plan is registered before results.
- Unit labour cost = labour cost ÷ driver units, consistent with the metric engine (§21.6).
19.7 Labour budgets and scheduling
-
Driver-based labour budget: seats from the plan's equipment and process hours, × FTE per seat from the roster, × fully-loaded rates from agreements. Fully-loaded rates include allowances, overtime expectations, FIFO travel, camp and payroll taxes.
-
Budgets are forecasts. They are registered (§10), and the actual-vs-budget variance is decomposed:
- volume (more seats needed);
- roster (FTE/seat);
- rate (agreements, overtime);
- absence;
- mix (contractor vs employee).
The decomposition is computed by the same bridge logic as AISC (§21.6), and the bridge must sum exactly (PO-PUSH-10).
-
Labour costs flow to FA as monthly summaries per cost centre with Merkle-folded detail (§21.3). Payroll is run by the payroll system of record, and FrankenMining never computes pay.
19.8 Guards, proof obligations and gates
| Guard | Condition | Action |
|---|---|---|
| G-MUST-1 | Individual-level performance metric requested without lawful basis, policy attestation and consultation evidence | FMINE-REF-3xx (authorization) |
| G-MUST-2 | Crew or individual ranking without intervals and covariate adjustment | Refuse the render |
| G-MUST-3 | A published plan needs seats that the roster cannot cover with qualified, unexpired people | Plan marked infeasible-labour; shortfall listed |
| G-MUST-4 | Hours-of-work or statutory-appointment rule would be violated | Hard refusal; never priced |
| G-MUST-5 | Restricted-lane fatigue or health data requested outside its policy | FMINE-REF-301-class authorization refusal |
| G-MUST-6 | A CCV campaign reports zero non-conformances over n verifications while an independent random audit gives P(X = 0) = (1 − p)ⁿ < α at its lower credible bound for p, or checklist answer entropy collapses (§19.5, GB-43) | Flag Conflicted(TickAndFlickSuppressionAlarm) and open an audit InvestigationCase; never render as verified-current |
| PO | Statement | Verification |
|---|---|---|
| PO-MUST-1 | Roster feasibility checker agrees with an independent brute-force checker on generated rosters | Property test |
| PO-MUST-2 | FTE-per-seat calculation reproduces hand-computed examples (GB-23) | Known answers |
| PO-MUST-3 | Labour variance bridge sums exactly to the total variance | Property test |
| PO-MUST-4 | Pseudonymization is stable within a tenancy and irreversible without the key held by the privacy officer role | Security test (§31) |
| Gate | Threshold (TARGET) |
|---|---|
| GATE-MUST-01 | Pilot: competency coverage check run against 12 months of rosters and training records; every historical gap found is confirmed by the site |
| GATE-MUST-02 | CCV evidence state live for ≥ 3 MUEs at the pilot with freshness policies attested by the site's safety function |
| GATE-MUST-03 | Privacy impact assessment and works-council review (where applicable) completed before any person-level data is ingested (§34.4) |
19.9 Galaxy-brain card (illustrative values)
GB-23 · FIFO 14/7 vs 8/6: cheaper per seat, but hours and fatigue are not for sale.
- Equation.
- FTE per seat = 8,760 h ÷ (12 h × 365 × on-fraction) ÷ (1 − absence).
- Cost per seat = FTE × (salary + trips × flight + on-site nights × camp).
- Substituted (absence 12%; salary $150k; flight $1,200; camp $150/night):
- 8/6: 2,503 h per person, 3.98 FTE/seat, 26.1 trips. Cost $845k per seat per year.
- 14/7: 2,920 h per person, 3.41 FTE/seat, 17.4 trips. Cost $707k per seat per year.
- Difference: $139k per seat, or about $55M/y across 400 seats.
- Intuition. Longer swings need fewer people and fewer flights. The saving is large enough that a cost-minimizing optimizer will always push toward longer swings and more consecutive nights.
- That is exactly why hours-of-work limits, maximum consecutive nights and fatigue thresholds are hard constraints, not costs (G-MUST-4). The DecisionCard shows the saving and the fatigue-risk profile, and a human chooses within the legal and agreed envelope.
- Assumptions. Same absence and the same annual salary across rosters (FIFO allowances often differ); flights per swing. 14/7 works 17% more hours, so the headline mostly reflects the salary assumption: at equal hourly pay ($175k for 14/7) the saving is about $53k per seat, or ≈ $21M/y. The DecisionCard shows both.
- Flip. Agreement or statute caps swings at 8 days → the 14/7 option disappears. Fatigue-event analysis shows night-block risk rising sharply after night 4 → the roster alternative with a mid-swing day/night swap is preferred.
GB-43 · CCV completion vs. a random audit: when "0 non-conformances in 300 checks" signals suppression.
- Equation. An independent random audit of m controls finds k defects, giving a Beta posterior for the true defect rate p. If routine CCVs report honestly, X ~ Binomial(n, p) and P(X = 0) = (1 − p)ⁿ. If they detect only a fraction q, X ~ Binomial(n, qp), and the likelihood ratio of X = 0 for q₁ against q = 1 is E = ((1 − q₁p)/(1 − p))ⁿ. Using the audit's lower credible bound for p keeps E conservative.
- Substituted (illustrative: n = 300 routine CCVs, X = 0; audit m = 30, k = 3, p̂ = 10%, Jeffreys 90% interval
3.7–21.7%):
- at p = 3.7%: P(X = 0) = 1.2 × 10⁻⁵, and E against q₁ = 0.1 is 2.7 × 10⁴ ≫ 1/α = 20;
- at p = 10%: P(X = 0) = 1.9 × 10⁻¹⁴;
- the 95% upper bound on qp is 1.0%, so q < 10% at the point estimate and q < 27% at the lower bound.
- Intuition. A completion count measures n, not the detection fraction q. CCV completion is a scorecard metric
at Barrick (5 points of the 70% scorecard, threshold 75%, maximum 85%, 2025 actual 84%; FACT, E601), so Muster
reports q beside n at every site. G-MUST-6 flags a contradiction as
Conflicted(TickAndFlickSuppressionAlarm). - Assumptions. The audit samples the same control population and shift mix.
- Flip. If an audit of m = 50 also finds no defects, and answer-entropy and photo-timestamp checks pass, the streak is corroborated instead of flagged.
Open questions.
- OPEN-MUST-1. Which HR, training and roster systems export what, under which privacy agreements, at the pilot.
- OPEN-MUST-2. Whether the company's CCV app data can be exported with verification-quality fields, not just completion.
- OPEN-MUST-3. Jurisdictions requiring works-council or union consultation before workforce analytics.