Helm II: the CapitalProgram, executive optimization and the scenario index
5,076 words10 subsections7 tables3 listingsPlan version 0.1
On this page10
Crates:
fmine-capital: candidates, programme, options, country regimes;fmine-econ: cash-flow models, fiscal terms, scenario index;fmine-calib::refclass: reference-class priors.
Source: B3 PQ-7. All galaxy-brain numbers are illustrative.
23.1 Verdict (Brenner pass B3, PQ-7)
| Hypothesis | Verdict | Role |
|---|---|---|
| H7a NPV/IRR plus hurdle rate | Rejected as the rule; retained as a reporting column | Ignores overrun bias, concentrates price beta, and makes exploration look NPV-negative. Hindcast evidence against: Tanami 2's estimate rose from $850–950M (Feb 2022, production 2024) to $1.7–1.8B (Feb 2026, production H1 2027), roughly 1.8–2.1×; Pascua-Lama was written down by $5.2B in Q2 2013 and $6.1B for the year (FACT, E631, E632, E633). |
| H7b Mean-CVaR over shared scenarios | Adopted as the risk layer | Always reported with selection frequency, never as a single "optimal portfolio" |
| H7c Real options plus bandit/Gittins indices | Staged-option valuation adopted; Gittins and regret guarantees rejected | Gittins needs independent arms, one arm played at a time, frozen idle arms and no budget coupling, and all are violated (shared price, regional geology, parallel programmes, tenure expiry, competitors). O(√T) regret bounds are vacuous at 10–30 decisions per decade. Indices are triage heuristics only. Option value is shown separately from static NPV to prevent option-value laundering. |
H7d Per-share two-stage stochastic CapitalProgram with recourse (forced alternative) |
Adopted as THE decision object | Contains (a) as a column, (b) as the risk layer and (c) as recourse |
23.2 Every capital alternative is one CapitalCandidate
| Type | First-stage action | Recourse | Cash-flow source | Key priors | Typical evidence class |
|---|---|---|---|---|---|
| Sustaining capex | Fund / defer | Catch-up later at higher cost; failure hazard | Pushback plan with vs without; hazard models (TSF §18, fleet §16, plant §17) | Failure hazards, overrun | ModelledUncalibrated |
| Brownfield expansion | Study → FEED → build gates | Delay, rescale, abandon | Plan delta under the same scenario index | Overrun, ramp-up, conversion | Modelled |
| Greenfield exploration play | Fund stage k | Advance, abandon, JV-out | Lodestar posterior (§11.5(B)) × V(m) (§23.5) × conversion × development path; 15.7–17.9-year lead time (FACT[U], S&P; E636) | Discovery probability, size, lead time | Elicited / Transferred |
| Junior equity stake | Buy x% | Top-up, ROFR, sell | Junior's public NI 43-101/JORC resource, haircut (§23.5); market price process | h_pub, conversion, P_dev, dilution | Transferred |
| Earn-in / option JV | Stage spend | Walk away / complete | As above, then own-drill data | Conversion | Transferred → Measured |
| M&A | Bid | Integrate, divest | Target assets as candidates on public data, plus synergies | Synergy realization (OPEN), premium. Build-vs-buy parity: greenfield median $18,200/tpa plus a 40% overrun ≈ $25,480/tpa, about equal to the 2020–26 copper M&A median of $25,182/tpa (FACT, FactSet 16 Jul 2026, E642; $18,048 is the all-project median) | Transferred |
| Stream or royalty sale | Sell x% of metal for deposit D | Buy-back clauses | Own production × price paths: the payout is scenario-dependent, like a put | Price paths | Modelled |
| Share buyback | Repurchase $C | — | ΔNAV/share = C·(NAV_ω/P − 1)/shares, which is correlated with the gold price, not risk-free | P/NAV, own NAV ensemble | Modelled |
| Dividend top-up | Pay | — | Policy (e.g. Barrick's 50% of attributable FCF; FACT, R6 §1.4) | — | Policy (attested) |
Sustaining capex is risk reduction, not an NPV project.
- Its payoff is the reduction in expected loss and in the CVaR of catastrophic events, such as TSF loss of containment (GB-21).
- Deferral lowers current AISC, because AISC includes sustaining capex (GB-26). The KPI therefore rewards deferral.
- Every sustaining card shows that hazard–AISC trade-off explicitly.
pub struct CapitalCandidate {
pub id: CandidateId, pub kind: CandidateKind, pub stages: Vec<StageGate>,
pub entity: EntityNodeId, // where the asset or spend sits in the CapitalEntityGraph
pub cashflows: CashflowEnsemble, // 100% basis, keyed by ScenarioIndex (common random numbers)
pub kpis: KpiEnsemble, pub tier_one: Option<TierOneAssessment>,
pub adjustments: Vec<ReferenceClassAdjustment>, pub evidence: EvidenceSummary,
}
pub struct StageGate { pub cost: CashflowEnsemble, pub reveals: InformationSpec, pub recourse: Vec<RecourseAction>,
pub approvals: Vec<PermitGate> /* authority, filed, statutory_clock, deemed_rule, reopen_thresholds */ }
pub struct CapitalEntityGraph { // parent, carve-out, JV and state-sharing waterfall (DESIGN)
pub nodes: Vec<EntityNode>, // Parent | CarveOut | NgmJv | PvJv | KibaliJv | TwigaJv | RekoDiqJv
pub edges: Vec<WaterfallEdge>, // equity %, funding or free carry, DSCR locks, repatriation, sharing
}
pub struct CapitalProgram { pub entity_graph: CapitalEntityGraph, pub candidates: Vec<CapitalCandidate>,
pub budget: Money, pub liquidity_floor: Money, pub cvar: CvarConstraint,
pub kpis: Vec<KpiConstraint>, pub objective: PerShareNav /* evaluated at Parent and CarveOut */ }
- Ownership tiers, JV waterfalls and the IPO perimeter (
CapitalEntityGraph; FACT plus DESIGN). A major does not receive 100% of asset cash flow, and its interest is not a constant multiplier:- Parent and carve-out. Barrick is evaluating an IPO of a small minority interest in a North American
company anchored by its NGM and Pueblo Viejo JV interests and the Fourmile discovery; under the 9 Aug 2026
agreement with Newmont, Fourmile is to be vended into NGM (FACT, E658, E629).
CapitalProgramevaluates each candidate's ΔNAV/share, AISC and FCF yield for both the parent and the carve-out, so vend-in terms and any inter-entity toll (§15.6 item 9) are priced on both denominators. - NGM (61.5% Barrick, 38.5% Newmont; E457) and Pueblo Viejo (60/40; E672). Growth candidates need partner funding or trigger the JV agreements' dilution terms (DESIGN; terms to be registered from the agreements).
- Kibali (45% Barrick, 45% AngloGold Ashanti, 10% SOKIMO; equity-accounted). Cash leaves the JV only as dividends or loan repayments. Royalties and charges total 5.7% of gold revenue including shipment fees, and the 50% super-profits tax applies to the increase in gross operating surplus when gold exceeds $2,000/oz (FACT, E242, E243).
- Twiga (North Mara and Bulyanhulu: 84% Barrick, 16% Government of Tanzania free-carried). The 50/50 division of economic benefits is kept by an annual true-up (FACT, E448), so state taxes, royalties, fees and the 16% dividend are tracked against the 50% share.
- Reko Diq (50% Barrick; 25% federal SOEs; Balochistan 15% funded and 10% free-carried; E302, E303). Project-finance cash sweeps and DSCR locks gate distributions, and Barrick recovers its funding of the free-carried share (DESIGN; terms to be registered).
- Parent and carve-out. Barrick is evaluating an IPO of a small minority interest in a North American
company anchored by its NGM and Pueblo Viejo JV interests and the Fourmile discovery; under the 9 Aug 2026
agreement with Newmont, Fourmile is to be vended into NGM (FACT, E658, E629).
- Permit gates (C5 §4.7). Early-works spend that proceeds while the main approval is pending is a real option
with regulatory recourse. A
PermitGaterecords the statutory clock, any deemed approval and the thresholds that reopen approval (E305, E306, E339).
23.3 The optimization
- Problem. Maximize E[ΔNAV_ω / shares_ω], since buybacks and issuance change the share count, subject to:
- Scale (TARGET).
- 50–500 candidates, typically ≤ 200 binaries after grouping mutually exclusive stage variants.
- 2,000 scenarios for optimization after Kantorovich reduction; ≥ 10⁴ for evaluation.
- Solver.
fmine-lp::milpto ≤ 0.5% gap in ≤ 10 min. Fallback: greedy plus a Lagrangian bound, with the gap reported. - The bottleneck is input validity, not compute. That is why reference classes, conversion haircuts and country processes (§23.5) get more design attention than the solver.
- Robustness. Minimax regret and Wasserstein DRO over contested scenario-family weights (§22.5).
23.4 The shared scenario index
pub struct ScenarioIndex { // one draw ω of the enterprise world
pub market: PricePathId, // Au, Cu, Ag, Sn, FX, diesel, power, carbon: joint process plus copula
pub inflation: CostPathId, // industry-wide cost factor (the common cause of overruns)
pub country: CountryPathId, // one regime path per country, shared by all assets in it
pub geology: RealizationSetId, // per-asset realization ids from Strata and Lodestar ensembles (§9.5)
pub execution: ExecDrawId, // per-project overrun, slip and ramp-up draws, plus a common factor
pub climate: ClimatePathId, // water balance and TSF scenarios (§18.4)
}
- Common random numbers across all candidates make comparisons paired and low-variance. Streams use Philox and
Sobol keyed by logical identity (lifted
fs-rand; §9.5). - Portfolio CVaR is computed only on joint draws, never by combining marginal distributions.
- Price-linked costs (royalties, profit-sharing, by-product credits) share the
marketdraw (§21.6). - Country regimes are a stochastic process, not a discount-rate fudge (B3 §6.5).
- Each country has a
CountryRegimeMarkov chain over {Stable, FiscalShock, SecurityDisruption, Suspension/Expropriation}. Operation-level states addRestricted{reagent | water}, distinct from suspension (Veladero's cyanide-addition restriction, 29 March–15 June 2017; E278, E281), andNOT_PUBLISHEDsite-quarters. - Impacts are cash-flow transforms:
- royalty or tax step-ups, including retroactive ones. Mali's Mining Code is Loi n°2023-040 of 29 Aug 2023 (JO 1 Sep 2023; FACT, E415). Its Art. 218 keeps valid permits on their original regime until renewal but gives the Code precedence over conventions (E421). Loulo-Gounkoto moved to the 2023 Code by settlement (24 Nov 2025; E410), and the Code was applied retroactively to 2024–2025: $200M of additional royalties, penalties and interest paid in April 2026 (FACT, E412, E413). The average royalty is now about 18%, against 6% under the 1991-Code conventions of the March 2023 report (FACT, E414, E246);
- suspension, loss of control, and post-settlement fiscal reset. Loulo-Gounkoto: export restriction Nov 2024, four employees detained 25 Nov 2024, gold stock removed 11 Jan 2025, suspension announced and initiated 14 Jan 2025, court-ordered six-month provisional administration and loss of control 16 Jun 2025 (administrator in day-to-day charge from 23 Jun), settlement 24 Nov 2025 ($253M paid 28 Nov), control returned 16 Dec 2025 (FACT, E248, E401–E409). Barrick's later footnote reports no operating data for Q1–Q3 2025; the first Q1 2025 publication carries production (22 koz at 100%) and withholds only per-ounce data, and FY2025 production is reported as 29 koz (FACT, E122, E477, E478; W1-DR-17). After the reset, H1 2026 production was 152 koz Au (64 koz in Q1; 88 koz in Q2 from 914 kt at 3.25 g/t and 92% recovery), with royalties of $585/oz in Q2 2026 ($629/oz in H1 2026); Q2 2026 TCC was $1,897/oz and AISC $2,240/oz, H1 2026 TCC $1,906/oz and AISC $2,104/oz (Barrick 80% basis; FACT, E483, E638, E670);
- portfolio exits that end a reported series: Tongon sold to the Atlantic Group for up to $305M, closed
1 Dec 2025; Hemlo sold to Carcetti Capital for up to $1.09B, closed 26 Nov 2025. Both keep their columns
with
—and numeric-zero placeholders in 2026 files (FACT, E485–E488, E553, E554); - tenure refusal and ownership reset: Porgera, where the State declined to extend the SML (24 Apr 2020), the mine was on care and maintenance from 25 Apr 2020 to 22 Dec 2023, and it reopened with Barrick's equity halved from 47.5% to 24.5% (FACT, E425–E432);
- contract annulment: Cobre Panamá (industry reference case), where Law 406 was declared unconstitutional on 28 Nov 2023, the mine has been under Preservation and Safe Management since, stockpile-only processing was approved on 7 Apr 2026, and as of 28 Oct 2026 the President is weighing a commission's recommendation to negotiate an orderly closure (FACT, E433–E442);
- slowdown with capex escalation (Reko Diq 2026).
- Each regime row carries its instrument (convention vs code) and an as-of date. Ready rows (FACT unless
marked; C3 §3.6; W2 §3):
- DRC/Kibali (as of 2026-02-27): Law 007/2002 as amended by Law 18/001 of 9 Mar 2018 (regulations 8 Jun 2018); the Art. 276 five-year stability on existing rights lapsed about Mar 2023 (INFERENCE). Statutory gold royalty 3.5% of gross commercial value (Art. 241, E445); Kibali's total royalty and charges are 5.7% of revenue including 2% shipment fees (E243; the TR's pages label it differently, E449), and it is exempt from the 2025 Finance Law's +2% export charge (E447). Super-profits tax 50% of profit from prices more than 25% above the BFS price, i.e. above $2,000/oz on Kibali's $1,600 (Art. 251 bis; E242, E446); CIT 30%; State 10% via SOKIMO. Permits: seven expire 11 May 2029 and three on 3 Jun 2030, against a LOM to 2043 (E245). Renewal is for at most 15 years each (Art. 67) and needs a new feasibility study proving reserves, financing, an approved ESIA update, profitability, fiscal compliance and a further 5% of equity to the State per renewal (Art. 80; E443, E444). The application window for the 2029 permits opened 11 May 2024 (INFERENCE). The TR summarises renewal as conditional only on fees and environmental standards, which is narrower than Art. 80.
- Mali/Loulo-Gounkoto (as of 2026-08-10): Loi n°2023-040, adopted by settlement in place of the 1991-Code
conventions; Somilo permit renewed for 10 years under it on 13 Feb 2026 (E411). Average royalty about 18% at
Barrick's $4,500/oz planning price: ISCP 5% of turnover, TAV 3–7.5% up to $2,500/oz plus 0.5 points per
$400/oz above, revenue funds 2.25%, stamp 0.6% (E414, E422–E424). CIT 30%. State 20%; the new-project
template is 10% free carry, a 20% cash option within 12 months and 5% to nationals, up to 35% (E416–E418).
Stability runs to the 10th anniversary of first commercial production and does not shield mining duties or
royalties (INFERENCE, E419). The royalty is a step function of price, so Helm draws it from the
marketdraw like Kibali's super-profits tax. - [superseded 2025-11-24] Mali/Loulo-Gounkoto (as of 2023-03): 1991-Code Establishment Conventions; royalty 6%; CIT 30%; minimum 0.75% of gross revenue; state 20% (E202, E246).
- PNG/Porgera (as of 2026-08-10): an agreement stack, not the code alone: the Porgera Project Commencement Agreement (effective 3 Feb 2022, completed 22 Dec 2023), Special Mining Lease 13 to New Porgera Ltd and a Fiscal Stability Agreement (both 13 Oct 2023). New Porgera is 51% PNG stakeholders (KMHL 36, MRE 5, other 10) and 49% Porgera (Jersey) Ltd, owned 50/50 by Barrick and Zijin; Barrick holds 24.5% equity and 23.5% of economic benefits, and PNG stakeholders receive 53% of lifetime benefits. The State may buy the 49% at fair value after 10 years (window from about Dec 2033, INFERENCE). FSA royalty and tax rates are FACT[U] (E425–E432).
- Panama/Cobre Panamá (industry reference case, as of 2026-10-28): no instrument in force. Law 406 (20 Oct 2023)
was struck down on 28 Nov 2023 (gazetted 2 Dec), and Law 407 (3 Nov 2023) bars new concessions and renewals.
The operating basis is the Preservation and Safe Management plan (30 May 2025) plus stockpile processing
(7 Apr 2026, "not a reopening"). Regime path: Stable → Suspension (28 Nov 2023 →) with a
Restricted{stockpile-only}sub-state from 2026 Q2 (E433–E442). - Tanzania/North Mara–Bulyanhulu (from 24 Jan 2020): the Twiga framework agreement under the Mining Act 2010 as amended in 2017. Royalty 6% plus a 1% clearing fee; the Government's 16% is free-carried from 1 Jan 2020; economic benefits are split 50/50 through an annual true-up that excludes the $300M settlement payment. Regime path: FiscalShock plus concentrate-export ban (3 Mar 2017 → 24 Jan 2020) → Stable (E135, E448).
- Reference class for host-state interruptions (W2 §4; label
Transferred, §23.5). Porgera: 3.66 years of care and maintenance, equity 47.5% → 24.5%. Cobre Panamá: at least 2.92 years and unresolved. Loulo-Gounkoto: 336 days suspended, 183 days without control, $537M paid in three tranches. Tanzania/Acacia: a 2.89-year export ban ending in a 16% free carry and 50/50 sharing. In three of four resolved or ongoing cases the owner kept or regained operation on worse fiscal or equity terms, and every resolution included a lump sum or a larger free carry (INFERENCE; Barrick- and First Quantum-heavy, not an industry base rate). - Price-contingent fiscal terms. Kibali's super-profits tax is excluded from reserve economics because $1,500 is below its trigger; Helm models it as a function of the price draw, so after-tax value departs from the technical report at any price above $2,000. An importer flags arithmetic that mixes decks: Kibali's COG table charges $85.5/oz royalty at a $2,000 price, which is 5.7% of $1,500, not of $2,000 (INFERENCE, E244).
- One regime path per country is shared by all assets in it.
- HYPOTHESIS H-FISC: fiscal-shock hazard rises with the metal price (windfall-seeking). That creates a negative price–regime correlation that caps upside, which a hurdle-rate model cannot express (OPEN-HELM-4).
- Priors come from structured elicitation (IDEA protocol, §10.6) plus a reference class, with Wasserstein DRO over hazard multipliers because these probabilities are contested.
- Each country has a
23.5 Priors that matter more than the solver
Reference-class priors for capex overruns and schedule slips (fmine-calib::refclass).
- Classes (FACT inputs):
- Bertisen & Davis, 63 projects: mean +14%, about half outside ±15%, about 1 in 13 at ≥ +100%;
- McKinsey (Nov 2024, 80 projects): 83% of recent major projects with cost or schedule problems, overruns
40%, delays 20–30%; megaprojects ≥ $1B: overruns ≥ 79%, delays 52% (FACT, E641);
- schedule in years: no sourced reference class yet (the earlier "1.2-year mean across 58 projects" has no located source; OPEN);
- lead time: 15.7 years (127 mines, 2002–23 starts) to 17.9 years (2020–23 starts) (FACT[U], S&P; E636).
- Hierarchy: industry class → company random effect → project. The company effect updates from the company's own approvals in its bitemporal record.
- Adjustments are explicit and visible (evidence class
Transferred), never buried in the discount rate. - Fit check (GB-32, DESIGN). Compare both a single lognormal and a core-plus-blowout mixture with the three registered targets. Before GATE-CAP-02 can qualify a historical fit, verify the paper's bias adjustment and event denominators. A corporate forecast needs its own declared reference class.
Resource conversion and public-resource haircuts.
- Reserve-equivalent R = h_pub · (c_IR·M_ind + c_FI·c_IR·M_inf), where:
- h_pub is the public-report haircut (junior-reported vs the major's re-estimate);
- c_FI is inferred → indicated conversion;
- c_IR is indicated → reserve conversion;
- P_dev is the development probability.
- Priors are Beta per deposit style × drill density × reporting code × price deck. They are learned from statement-to-statement flows in the company's own reserve history, junior filing histories and post-acquisition re-estimates.
- Price decks differ. Barrick reserves at $1,400 or $1,500/oz (FACT, R6 §1.3); its gold deck was $1,200 (2020–21), $1,300 (2022–23), $1,400 (2024) and $1,500 (2025) (FACT, E143). Juniors and PEAs often use higher decks (Fourmile's $1,900; E141). Re-price before haircutting.
The value function of an undiscovered deposit (the Lodestar interface; resolves OPEN-LODE-5 as DESIGN).
- V(m) = E_ω[NPV of development | mark m = (metal, size, grade, depth, style, jurisdiction)]. It is built from:
- capital-intensity reference classes (FACT, R6 §4.3);
- the lead-time distribution;
- P(develop | discovered);
- the fiscal regime;
- price paths.
- Every exploration play and junior stake is valued on the same scenario index as the operating assets.
- V(m) is a model, labelled
ModelledUncalibrateduntil hindcast against real discoveries' outcomes (the Lodestar hindcast protocol, §11.6).
23.6 Executive pay metrics as constraints with published prices: the KPI price list
| Metric (weights FACT, R6 §1.5, §2.5) | Treatment | Why |
|---|---|---|
| AISC; Newmont adjusted CSC/GEO (35%) | Soft constraint per site-year; shadow price published | A ratio metric: high-grading, deferral or reclassification can move it without changing value (GB-26) |
| ROCE (Barrick 15% LTI, 10–15% range; Newmont 30% PSU) | 3-year floor constraint; shadow price | Penalizes long-gestation growth, because capital employed rises years before EBIT: a structural bias against greenfield made visible |
| Reserve replacement (3-year, 15% LTI) | Computed by fmine-metrics under one definition; a constraint only after the definition is reconciled (190% vs 504%) |
Rises with acquisitions or a higher deck as well as with discovery |
| GEO (25% API) | Soft floor, on a named ratio basis (GB-27) | Volume can conflict with NPV; GEO moves with the price ratio |
| rTSR vs GDX (35% Barrick; 60% Newmont) | Excluded from optimization; context only | Not controllable; market-relative |
| FCF/share, dividend policy | Liquidity constraints and minimum-cash floor | Real harm when breached |
| Safety and critical controls | Hard constraints, never priced | E023; not tradeable (G-HELM-1) |
The KPI price list (board artifact). It answers questions such as:
- "Holding 2027 Au AISC ≤ $X/oz costs $Y M of E[NAV]."
- "Relaxing the ROCE floor from 12% to 10% admits greenfield G, worth +$Z/share."
Each answer is a constraint dual with a validity range from post-optimality analysis.
Monitor M-HELM-8 (Goodhart alarm). It fires when a KPI's shadow price exceeds 5% of programme E[NAV]. The board sees the price, and FrankenMining never adjusts KPIs automatically.
23.7 How a board sees it
┌ DC-2027-CAP-014 "FY27 growth envelope $800M" color: ESTIMATED (weakest input: country hazard, elicited) ┐
│ Alternatives (incl. do-nothing, buyback): A+E | A+D | E+D | A+E_stream | hold cash │
│ E[ΔNAV] $M: 372 | 241 | 253 | 376 | 0 CVaR20: −210 | −131 | −283 | −150 | 0 P(Tier One E): 0.31 │
│ Selection frequency (200 bootstraps): A 0.97, E 0.62, D 0.41, E_stream 0.58 → "E is fragile" │
│ Regret (mean/max): A+E 91/377 | A+D 222/701 | E+D 210/550 │
│ Chosen under board risk appetite CVaR20 ≥ −150: A+E_stream (binding). Without the stream: A+D, −$131M │
│ What would change it: E's S1 loss > $150M after stream; stream PV cost > $135M; P/NAV < 0.66 → A+D │
│ KPI prices: AISC FY27 cap $1,650/oz → −$38M; ROCE floor 12% excludes a greenfield G (−$0.21/sh) │
│ Reference-class adjustments shown: capex ×1.14 mean (mixture, GB-32), slip +1.2y; conversion h_pub 0.85 │
│ Best next information: EVSI(E metallurgy testwork) $41M vs cost $6M → fund before FID (GB-29) │
│ Sign-offs required: QP/CP (resources), CFO (financing), Board. execution_authorized = false (E023) │
└────────────────────────────────────────────────────────────────────────────────────────────────────────────┘
All numbers in this card are illustrative (GB-30).
23.8 The Tier One screen, juniors and deal structures
- The Tier One screen is versioned.
- Gold: Barrick's definition at a $1,400 (Circular) or $1,500/oz (Q2 2026 release) deck, ≥ 10-year life, ≥ 500 koz/y, lower half of the cost curve.
- Copper: $3.00 or $3.25/lb, ≥ 5 Mt, ≥ 20 years, ≥ 200 ktpa (FACT, R6 §1.3). The Sep 2025 copper definition ($3.00/lb, +5 Mt) is confirmed in the corpus (FACT, E134).
- The output is P(Tier One) over the ensemble plus a distance vector, not pass/fail.
- MinEx's Tier 1 definition is a different object, and the two are never mixed.
- Junior investment logic. The haircut machinery (§23.5) turns a junior's market price into the conversion it implies (GB-31). A staged earn-in buys information, and its value is option value shown separately.
- Deal terms are recourse structures (stake, top-up rights, ROFR, information rights, earn-in stages). The
ProgramOption{deal}from Lodestar §11.5(E) is the same object. - MNPI. Junior and M&A analysis is a walled lane. Public-basis and full-basis posteriors are kept separate (§11.7, §31.1), and every deal card carries its insider-list membership. Intra-JV transfers (Fourmile into NGM at fair market value; E139) are walled from the JV partner's view.
23.9 Monitors, guards, proof obligations, assumptions and gates
Monitors:
- M-HELM-5: capex and slip tracking. Alarm when P(final > AFE) > 0.5 under the project's posterior.
- M-HELM-8: the Goodhart alarm (§23.6).
- Country regime state changes trigger programme recomputation, with the liquidity floor binding first.
| Guard | Condition | Action |
|---|---|---|
| G-CAP-A | A capital card without reference-class adjustments shown | Refuse |
| G-CAP-B | Portfolio CVaR computed from marginals | Refuse |
| G-CAP-C | Selection frequency < 0.8 | Flag "fragile"; show runner-up |
| G-CAP-D | Option value merged into static NPV without a separate line | Refuse (option-value laundering) |
| G-CAP-E | Tier One definitions mixed | Refuse |
| PO | Statement | Verification |
|---|---|---|
| PO-PUSH-8 | The CVaR LP equals the sorted-tail average | Property test against fs-robust::empirical_cvar |
| PO-PUSH-12 | Calibration claims hold (binomial CI or e-process) | Ledger tests |
| PO-CAP-1 | Brute-force parity on ≤ 20 binaries | Known-answer test (GATE-CAP-01) |
| PO-CAP-2 | Per-share objective is invariant to share-count units; buyback ΔNAV formula reproduces hand examples | Known answers |
| ID | Assumption | Measured by | If false |
|---|---|---|---|
| A-CAP-1 | The scenario index captures the dominant correlations (price–cost, country–price) | Bootstrap stability; sensitivity to P/NAV, α and hazard multipliers | DRO over family weights |
| A-CAP-2 | Reference classes transfer to this company | Company random effect; M-HELM-5 | Widen; company-only after ≥ 10 projects |
| A-CAP-3 | The P/NAV model is adequate for buyback valuation | Sensitivity test | Report the P/NAV-conditional hurdle |
| A-CAP-4 | Conversion priors are learnable from statement histories | Data audit (OPEN) | Elicited priors, flagged Elicited |
| Gate | Threshold (TARGET) | When |
|---|---|---|
| GATE-CAP-01 | Brute-force parity on ≤ 20 binaries; CVaR LP equals the sorted tail | M4 |
| GATE-CAP-02 | Reference-class prior reproduces Bertisen & Davis's three statistics within ±0.03 | M4 |
| GATE-CAP-03 | Bootstrap selection frequency reported on every card | M4 |
| GATE-CAP-04 | Bitemporal hindcast of ≥ 5 past approvals (as known at approval) scored against realized outcomes; H7a vs H7d decisions compared | M4–M5 |
| GATE-CAP-05 | Synthetic exploration district: 50 synthetic decades comparing static NPV rank, Gittins heuristic, Thompson, knowledge gradient and staged-option policies on discoveries and NAV per $ | M4 |
23.10 Galaxy-brain cards (illustrative values)
GB-30 · CVaR capital allocation, and why the buyback is not a hurdle rate.
- Set-up. Five joint scenarios stand in for ≥ 2,000: S1 low price plus overrun; S2 low; S3 base; S4 high; S5 country shock. The budget of $800M buys two $400M packages.
- Packages (ΔNAV in $M by scenario).
- A, brownfield: [−60, 40, 220, 480, 220], mean 180.
- E, greenfield in a fiscal-risk country: [−150, 60, 420, 960, −330], mean 192.
- D, buyback at P/NAV 0.85, with own-NAV multipliers [0.70, 0.85, 1.0, 1.4, 0.95]: 400(m/0.85 − 1) = [−70.6, 0, 70.6, 258.8, 47.1], mean 61.2.
- Combinations.
- A+E: mean 372, CVaR −210.
- A+D: mean 241.2, CVaR −130.6.
- E+D: mean 253.2, CVaR −282.9.
- Result. NPV rank and minimax regret pick A+E (max regret 377 vs 701). Under the board's risk appetite τ = −150, A+D is chosen, so the price of risk appetite is $130.8M.
- Adding a stream on E (deposit $120M, scenario cost [60, 80, 130, 260, 50], roughly fair) gives E_s = [−90, 100, 410, 820, −260]. A+E_s has mean 376 and CVaR −150, and is chosen.
- Intuition. The buyback is a levered bet on the company's own NAV, not a risk-free hurdle. The stream is bought as tail insurance, not as cheap money.
- Flip. Stream PV cost > $135M → A+D. P/NAV < 0.66 → A+D overtakes on the mean. S5 hazard ×2 under DRO → re-rank.
GB-31 · A junior's market price implies 93% conversion of inferred ounces.
- Equations. R = h_pub(c_IR·M_ind + c_FI·c_IR·M_inf) and NAV = R·v·P_dev.
- Substituted.
- M_ind = 1.0 Moz and M_inf = 3.0 Moz; h_pub = 0.85, c_IR = 0.75, c_FI = 0.45, v = $300/oz, P_dev = 0.65.
- So R = 1.498 Moz and NAV = $292M, against a market capitalization of $350M.
- Options.
- Acquisition at a 35% premium ($472.5M) → −$180M.
- A 19.9% stake at market → −$11.5M.
- A 51% earn-in. K₁ = $35M reveals c_FI, and the same drilling revises the development probability:
{c_FI = 0.75, P_dev = 0.80 with p = 0.35, giving NAV $497M; c_FI = 0.29, P_dev = 0.55 with p = 0.65, giving
NAV $197M}, then K₂ = $110M. (Prior-mean P_dev = 0.64 ≈ 0.65.)
- Good branch: 0.51·497 − 110 = 143.6. Bad branch: 0.51·197 − 110 = −9.5, so walk away.
- Value = 0.35·143.6/1.08 − 35 = +$11.5M, of which the staging option is worth $5.8M.
- Acquisition break-even. 0.85(0.75 + 2.25·c_FI)·300·0.65 = 472.5 gives c_FI = 0.93. The price implies that 93% of inferred ounces convert.
- Intuition. Buy information (the earn-in), not ounces.
- Flip. The company's own-history c_FI prior ≥ 0.6 with tight spread, or P_dev ≥ 0.85 → the gap narrows. The junior refuses terms → stake plus information rights.
GB-32 · Check both ordinary capital-cost overruns and the risk of doubling.
- TARGET. For X = final ÷ feasibility-study capex, compare E[X] to 1.14, P(|X − 1| > 0.15) to 0.5 and P(X ≥ 2) to 1/13. FACT (E026, R7 §9.1): Bertisen & Davis (2008) studied 63 international mining and smelting projects. Their abstract qualifies its accuracy finding for estimation bias and recommends a shifted lognormal. OPEN (bd-2jow): verify how the study computes that band and the underlying denominators before treating these targets as historical frequencies. Bertisen & Davis, 2008
- Unshifted lognormal control. Fitted to the mean and tail (μ = 0.020, σ = 0.472), it gives P(|X − 1| > 0.15) = 0.75, not about 0.5.
- DESIGN, illustrative mixture. With probability 0.923, draw X from a normal with mean 1.043 and standard deviation 0.20 conditioned on X > 0. With probability 0.077, set X = 2.3. The point mass specifies the blowout distribution sufficiently to compute its tail and quantiles.
- INFERENCE under those assumptions. The mean is 1.13979, the fraction outside ±15% is 0.50490 and the probability of at least doubling is 0.07700. All three fall within the planning tolerance. The 90th percentile falls below 2.3, at quantile 0.90/0.923 of the positive core, or X = 1.43527.
- Illustrative application. At a $1.6B feasibility estimate, this declared model gives a mean of $1.82B, P90 of $2.30B and a 7.7% probability of reaching $3.2B. Applying it to a mine requires evidence that the mine belongs to the reference class.
- Flip. The company's own ≥ 10 approvals show a lighter blowout share → a narrower posterior. The class choice (megaprojects vs Bertisen & Davis) is itself a decision (OPEN-HELM-5).
Open questions (B3 §8.4, carried):
- OPEN-HELM-1. Conversion and h_pub datasets.
- OPEN-HELM-2. Stream and royalty market cost of capital.
- OPEN-HELM-3. Whether the CFO accepts P/NAV valuation of the company's own shares.
- OPEN-HELM-4. Is H-FISC (price-dependent fiscal hazard) supported by data?
- OPEN-HELM-5. Reference-class choice: megaprojects vs Bertisen & Davis.
- OPEN-HELM-6. Who signs the risk appetite τ? (The board; mechanism OPEN.)