Pushback: mine planning and optimization under uncertainty

5,866 words11 subsections8 tables3 listingsPlan version 0.1

On this page11
15.1 Verdict (Brenner pass B3, PQ-3)15.2 The three-gap ledger and the PlanCertificate15.3 Hierarchy, horizons and timescale separation15.4 Solver stack: build in pure Rust, with lab oracles only15.5 Open pit, underground and transition specifics15.6 Optimal ore mix at best unit cost15.7 Grade control: dig lines under uncertainty15.8 Schedule compliance as a forecastable, calibrated quantity15.9 Guards, monitors and proof obligations15.10 Galaxy-brain cards (illustrative values)15.11 Assumptions, gates, kills and open questions

Pushback answers three questions:

  • what to mine;
  • when to mine it;
  • where each tonne goes.

It answers them with plans that state how far from optimal they are, how much of that statement rests on a finite scenario sample, and how wrong the inputs have historically been. Its crates are fmine-plan (models and policies), fmine-optimize (closure and decomposition solvers, stochastic programming) and fmine-lp (certified first-order LP and a small MILP). Haulage simulation lives in Headframe (fmine-ops::haul, §16.4).

15.1 Verdict (Brenner pass B3, PQ-3)

Hypothesis Verdict Role in FrankenMining
H3a Deterministic chain: kriged model → Lerchs–Grossmann/pseudoflow pit → revenue-factor shells → pushbacks → MILP schedule at fixed cut-off → DCF with ± sensitivities Rejected as the decision basis Retained as (i) the parity baseline in every PlanCertificate, (ii) the shell and pushback skeleton generator, and (iii) the single-price-deck rendering the reporting codes require. VSS is undefined without it.
H3b Simultaneous stochastic optimization of the mining complex (COSMO-style) Conditional adopt Admitted only through the three-arm out-of-sample VSS gate (GATE-PUSH-STO). The default stochastic engine is SAA over the BZ LP relaxation with non-anticipativity by Lagrangian or progressive hedging. A metaheuristic solve with no attached bound is never published as "optimal".
H3c Information acquisition as a decision (EVSI, adaptive policies) Adopt narrowly InformationOptions on discrete commitments: pushback start, plant expansion, cave footprint, TSF raise (§22). Whole-mine POMDP rejected for v1: published successes are 2D, synthetic and noiseless, and wrongly abandoned 32% of multi-body cases (FACT, R7 §1.10).
H3d Hierarchical decomposition with certified gaps at every level (forced alternative) Adopt as the architecture Strategic, tactical and short-term layers pass targets and prices down and attainment up. Every plan carries the three-gap certificate. Algorithmic novelty: checked null. The novelty is the certificate discipline.
H3e Policy search over a frozen geometric skeleton (second forced alternative) Adopt The tactical cut-off, stockpile-reclaim, blend-target and pushback-trigger policy layer. It is legible to operators and costs a fraction of COSMO.

15.2 The three-gap ledger and the PlanCertificate

The decomposition is the single most important honesty device in planning:

reported_value − true_value = (z_model − z*_model)       optimization gap   (certified by a verified dual bound)
                            + (z*_model − z*_population)  sampling gap       (SAA statistical confidence interval)
                            + (z*_population − z_truth)   calibration gap    (synthetic truth, then reconciliation history)

The third term is often the largest in mining (FACT inputs, each a single source):

  • a Localised Uniform Conditioning case with slope of regression ≈ 0.1 against grade control (FACT[U], page not pinned in the corpus; E029). The mechanism is b ≈ ρ for any variance-restoring estimator (GB-11; E355);
  • only 21% of 412 interpreters identified the correct tectonic setting of one synthetic seismic image in Bond et al. 2007 (FACT, E639);
  • conditional simulations rarely validated against outcomes (R7 §11.5).

So a "0.1% from optimal" headline on a miscalibrated model is a false-certainty number. FrankenMining renders it with colour Estimated and an "uncalibrated" banner (NL-1…NL-8, §7.3).

pub struct PlanCertificate {                       // attached to every published plan, at every horizon
    pub plan: PlanId, pub model: ModelDigest, pub opt_set: RealizationSetId,
    pub primal: Money, pub bound: Option<CertifiedBound>, pub opt_gap: Option<Ratio>,
    pub saa: Option<SaaGap>, pub vss: Option<VssCertificate>, pub execution: Option<ComplianceAdjusted>,
    pub calibration: CalibrationStatus,            // Calibrated{ledger_ref} | Uncalibrated | Miscalibrated{correction}
    pub color: Color, pub refusals: Vec<Refusal>,
}
pub struct CertifiedBound { pub value: Interval<Money>, pub kind: BoundKind, pub witness: ContentHash, pub verified_by: VerifierId }
pub enum BoundKind { ClosureExact, BzLpRelaxation, Lagrangian { iters: u32 }, PdlpDualRepair, SaaStatistical { conf: f64, batches: u16 } }
pub struct VssCertificate {                        // the constructor refuses eval_set == opt_set or unpaired draws
    pub det_plan: PlanId, pub sto_plan: PlanId, pub eval_set: RealizationSetId, pub n_eval: u32,
    pub vss_oos: Interval<Money>, pub vss_in_sample: Money, pub optimism: Money, pub truth_vss: Option<Interval<Money>>,
}
pub struct ShadowPrice { pub constraint: ConstraintId, pub units: UnitExpr, pub dual: f64, pub valid_range: (f64, f64) }

What profit means here (DESIGN). "Maximize profit" means maximizing E[discounted free cash flow], and at enterprise level E[ΔNAV per share] (§23). It does not mean accounting profit. Accounting profit sits downstream of DD&A, stripping-cost capitalization (IFRIC 20) and impairment policy (E021), which FA renders (§21).

15.3 Hierarchy, horizons and timescale separation

Level Cadence Decision content Methods Passes down Reports up
Strategic (life of mine) Annual, or on trigger Ultimate pit, pushbacks, underground envelope and mining method, LOM schedule by phase-bench, plant capacity and expansions, cut-off policy seed Pseudoflow UPIT and parametric shells; BZ LP relaxation of PCPSP; Lagrangian bounds; TopoSort plus local search; SAA when gated Phase/bench tonnage and metal targets; dual prices ($/t mill hour, $/t blend tolerance, $/t stockpile capacity) Plan certificate; reserve rendering at the disclosure deck (§24)
Tactical (budget, quarter, month) Quarterly/monthly, plus hysteresis triggers Sequence within the strategic envelope; stockpile policy; blend targets; equipment and crew allocation SAA over the realization ensemble; H3e policy search; blend LP Monthly faces, blend bands, stockpile thresholds Attainment, compliance, F-factor posteriors
Short-term (week, shift) Weekly and per shift Dig sequence, dig lines, blend targets, dispatch targets (advisory) Receding-horizon MPC (LP/QP over 1–2 weeks); expected-loss dig lines (§15.7) Recommended targets as prepared effects (never actuated, §31.3) Shift actuals, reconciliation residuals

Separation rules (DESIGN):

  • Cadences differ by at least 12× (strategic vs tactical) and 4× (tactical vs short-term). The MPC runs per shift with a 1–2 week prediction horizon.
  • The tactical plan is re-solved only when a trigger fires:
    • an eproc alarm on compliance or reconciliation drift;
    • the price leaves its declared band;
    • a geotechnical, plant or tailings event occurs.
  • Plan churn is tracked as a KPI (HYPOTHESIS: churn is itself a cause of low schedule compliance). Re-planning on noise is a measurable defect.

15.4 Solver stack: build in pure Rust, with lab oracles only

Structural fact (HYPOTHESIS, high confidence). Strategic scheduling is mostly maximum-closure plus a few coupling rows per period. Bienstock–Zuckerberg (BZ) and Lagrangian relaxation both reduce it to closure subproblems. So the hard kernel is one pseudoflow implementation, which also serves the ultimate pit and nested shells. The BZ master LP is small and dense, which frankenscipy's in-universe simplex/IPM handles (FACT, B3 V2: fsci-opt/src/linprog.rs:83–120 names its methods Highs* but runs its own revised simplex and Mehrotra IPM; there is no HiGHS dependency).

Module (B3 name) What Algorithm Scale TARGET Lab oracle
fmine-optimize::pitflow (fm-pitflow) Ultimate pit, parametric nested shells, closure oracle Hochbaum pseudoflow on i64 CSR. Overflow guard: Σ|vᵢ| < 2⁶², else refuse. Implicit precedence arcs from slope templates (azimuth sector × geotechnical domain from §14.2). Parametric λ warm-started across revenue factors. Returns the cut and the flow, so closure is independently checkable MineLib UPIT exact. 10⁷ blocks / ~2×10⁸ implicit arcs ≤ 120 s, ≤ 32 GB MineFlow (MIT C++); fsci-sparse maximum_flow on small int32-scaled instances (it refuses capacities outside int32, FACT B3 V3); fnx preflow_push
fmine-optimize::bz (fm-bz) PCPSP / multi-period LP relaxations BZ partitions; master on fsci-opt linprog; subproblem on pitflow MineLib PCPSP LP within 1e-6 relative of the oracle; 10⁶ blocks × 20 periods ≤ 30 min HiGHS
fmine-optimize::lag (fm-lag) Lagrangian or proximal bundle relaxation of blend and multi-processor rows Every iterate is a valid dual bound Always-valid bound; gap ≤ 5% HiGHS
fmine-optimize::toposort (fm-topo) Feasible incumbents from LP solutions TopoSort (Chicoisne et al. 2012) plus local search and repair; checked in fmine-verify Gap ≤ 3% on ≥ 80% of MineLib PCPSP instances, ≤ 5% on all MineLib best-known values
fmine-lp::pdlp (fm-pdlp) Large sparse non-closure LPs: multi-site blend networks, SAA extensive forms, CVaR LPs Restarted PDHG with diagonal preconditioning. Certified bound by dual repair plus outward interval rounding, copying the fs-truss PDHG certificate pattern (FACT, B3 V4; that crate depends on fs-exec and fs-solid, so it is not lifted) 10⁷ nonzeros to 1e-4 relative gap ≤ 30 min, with bound HiGHS IPM; OR-Tools PDLP
fmine-lp::milp (fm-milp) Small MILP: blend with on/off, fleet assignment, pushback selection, capital programme (§23) Sparse bounded dual simplex with warm start, bound-tightening presolve, best-bound plus diving; cuts only if a gate demands them; MPS I/O ≤ 10⁴ variables, ≤ 500 binaries, ≤ 1% gap ≤ 10 min HiGHS, CBC; fsci-opt milp (dense rows, 2,048-node default, FACT B3 V1)
fmine-optimize::stoch (fm-stoch) SAA, Kantorovich scenario reduction, Mak–Morton–Wood bounds, VSS_oos, progressive hedging Common random numbers across candidates; disjoint optimization and evaluation sets enforced by type S ≤ 200 in optimization; ≥ 10³ in evaluation Brute force on toys
fmine-plan::sched (fm-sched) Strategic and tactical scheduling models (open pit and underground) Model builders over the solvers above — —
fmine-plan::blend (fm-blend) Blend and destination LP with grade-binned stockpiles (§15.6) — HiGHS parity 1e-7 HiGHS
fmine-plan::cutoff (fm-cutoff) Lane cut-off seed plus H3e policy search CMA-ES lifted with provenance (fs-dfo depends on fs-exec, so the algorithm is lifted rather than the crate, FACT B3 V6) — —
fmine-plan::mpc (fm-mpc) Shift/week receding horizon LP/QP; infeasibility fallback is the last feasible plan plus slack ≤ 5 s per solve HiGHS
fmine-plan::compliance (fm-compliance) Schedule-compliance forecasts (§15.8) Beta-binomial hierarchy plus eproc — —

NONGOAL-006 restated. FrankenMining does not build a general commercial MILP. The fmine-lp::milp scale ceiling is a design limit, not a temporary one.

Lab oracles (DESIGN).

  • HiGHS (MIT), CBC (EPL), MineFlow (MIT) and OR-Tools PDLP (Apache) live only in fmine-oracles. Gurobi and CPLEX are used only where a client's lab licenses them.
  • Pseudoflow is the production algorithm at Carlin (2024) and Turquoise Ridge (2023), for pit shells and for underground stope net-value selection; Cortez (2021) still used Whittle Lerchs–Grossmann (FACT, E186). The parity oracle therefore covers both LG and pseudoflow, because the algorithm changes between filings.
  • Every oracle is version-pinned, and its outputs are frozen as fixtures that are never regenerated from the candidate.
  • No oracle appears in the runtime or CI dependency graph. Fixtures are produced by a separate lab runner (§33.2).

UntrustedCandidate import (DESIGN; OPEN-PUSH-1 for owner sign-off).

  • FrankenMining exports MPS plus a certificate request.
  • Any external solution, such as one from a client's Whittle, Deswik, COMET or Gurobi, can come back as an UntrustedCandidate.
  • fmine-verify (std-only) checks feasibility and recomputes the objective independently. The candidate may become the incumbent.
  • Its claimed bound is ignored unless a dual witness verifies.
  • Why this matters: it lets FrankenMining sit beside incumbent planning software (NONGOAL-001) and certify its plans, rather than compete with it. The verifier stays the authority, which keeps "one authority per number".

15.5 Open pit, underground and transition specifics

Topic Design Status
Slope templates Precedence arcs generated from Highwall sector angles per geotechnical domain and azimuth (§14.2). Changing a slope angle is a new geotech claim, and it re-stales the shells. DESIGN
Pit and ramp design Designed pits are engineers' acts in their CAD tools. FrankenMining ingests the designed pit as an L5 DesignSolid and computes the shell-to-design loss (tonnes, metal, value) with uncertainty, plus ramp-induced slope flattening. No CAD is built (NONGOAL-001). DESIGN
Stope optimization fmine-plan::stope: floating-stope / mineable-shape optimization over realizations. Dilution comes from the ELOS card (§14.3) and minimum mining width from the method. The output is P(stope economic) and expected value per candidate shape. These heuristics have no bound, so they are labelled heuristic (guard G-PUSH-3), and solutions from MSO-class client tools import as UntrustedCandidates. DESIGN; heuristic
Underground scheduling An activity network covers development metres, stope cycles (drill, blast, muck, backfill pour and cure), and ventilation and services prerequisites. The critical path and max-cycle-mean bounds come from max-plus algebra (lifted fs-tropical, FACT E003). Resource-constrained scheduling uses fmine-lp::milp up to ≤ 10⁴ variables, and priority-rule heuristics with a reported bound beyond that. DESIGN
Open pit → underground transition The transition depth and crown pillar are a CapitalCandidate (§23) over the shared scenario index, not a fixed design input. DESIGN
Caving (block/panel) Footprint selection, draw-point scheduling and dilution entry are Phase 2 and research-grade. Laubscher-style empirical cards only (OPEN-HIGH-3). OPEN
Waste dumps and PAG Dump destinations sit in the destination LP with an encapsulation constraint: NAF cover tonnes ≥ r × PAG tonnes per cell and period, with r as policy data. If a block's ARD class is unknown, no NAF-dump destination is offered (FMINE-REF-402, §18.5). DESIGN
Dilution attributes Dilution material carries its deleterious attributes, not only zero grade: Turquoise Ridge underground dilution carries in-situ TCM at 0 g/t Au, which raises TCM/Au and lowers recovery (FACT, E187). Residual dilution and ore loss are attributed to four registered sources: internal, planned, accidental (→ Highwall, Headframe) and geologic (→ Strata) (E399). DESIGN
Haul distances Taken from the haul-road network geometry per period (Headframe §16.4). They change with pit depth and dump fill, so haulage cost is a function of the schedule, not a constant. DESIGN

15.6 Optimal ore mix at best unit cost

This answers GOAL-011. It is the core of "what should we feed the mill, and from where?"

Blending and destination LP (DESIGN).

Indices:

  • s: a source or parcel (a block, a bench-phase, or a stockpile grade bin);
  • p: a destination (CIL, flotation, heap leach, POX, waste dump cell, stockpile bin k);
  • t: a period.
max Σ_t δ_t [ Σ_{s,p} x_spt (NSR_sp − c^proc_p − c^haul_sp(t)) − Σ_s c^mine_s m_st − f_t ]
s.t.  Σ_s x_spt ≤ Cap_p,t                                (tonnes)
      Σ_s x_spt · E_s ≤ P_p · H_p,t                      (energy: E_s = specific energy kWh/t from the hardness proxy, §13.4)
      Σ_s x_spt (a_s,e − A^max_p,e) ≤ 0                   (deleterious e: As, Hg, Sb, Bi, F, Cl, CN-soluble Cu, organic C, PRI)
      Σ_p x_spt = m_st ;  precedence/closure on m        (envelope from pitflow / bz)
      I_k,t+1 = I_k,t + inflow_k,t − reclaim_k,t ; 0 ≤ I ≤ Î_k     (grade-binned stockpiles)
      NAF_cover_t ≥ r · PAG_t per dump cell               (§15.5, §18.5)
NSR_sp = Σ_metal g_s,m · R_p,m(domain_s) · payable_p,m · (price_m − TC/RC/refining_m) − penalties_p(s) − royalty_m(price)

Design choices, each with its reason:

  1. Recovery is per source geometallurgical domain, not per blend. This keeps recovered metal linear. Blend-dependent recovery uses piecewise-linear domain-mix classes. Recovery applies at a declared processing support, a shift or day blend (§17.3).
  2. Hardness enters as specific energy under mass-weighted additivity. Hardness indices are non-additive (§13.4), so this is HYPOTHESIS H-ADD: kWh/t is additive within ±8% over the operating blend range. It is validated on plant data. If falsified, the model uses piecewise blend classes.
  3. Stockpiles use fixed grade bins. Exact mixing is bilinear and non-convex.
    • Certificate: a McCormick relaxation of the bilinear model gives a valid upper bound.
    • TARGET: binned-LP vs McCormick gap ≤ 1%.
  4. The throughput–recovery trade-off is explicit.
    • Grind modes m (fine, medium, coarse) carry pairs (Q_m t/h, ΔR_m), and the LP picks a convex combination per period.
    • The dual on mill hours says whether to "push tonnes". Tin needs the coupled comminution model because its recovery is strongly size-dependent and fines are lost (§17.3).
  5. All payable metals are in the NSR. By-product vs co-product treatment is a presentation layer for AISC and C1 (§21.6) and never changes the optimization.
  6. Royalties and price-linked costs are functions of the same price draw as revenue. The +16% industry AISC rise in Q1 2026 was driven by royalties and corporate G&A (FACT, R6 §4.2).
  7. Blend windows have two registered forms, and refractory circuits add two-sided windows and campaign modes (FACT plus DESIGN). A window can enter pit optimisation as linearised per-block penalties (Turquoise Ridge: an acid cost when CO3 > 4.3% and a credit when CO3 < 3.7%, mirroring the 3.5–4.3% feed window) while hard annual caps apply only in scheduling (FACT, E180). Roasters and autoclaves need two-sided windows: too little sulphide sulphur starves a roaster of heat, and too much sulphide or carbon overloads it. For refractory circuit p, element e and period t, with campaign mode y_{p,t}: L_{p,e}(y_{p,t}) · Σ_s x_{spt} ≤ Σ_s a_{s,e} x_{spt} ≤ U_{p,e}(y_{p,t}) · Σ_s x_{spt}.
    • Goldstrike roaster (Carlin TR Table 13-7): SS 0.8–1.8% (optimum 1.6), CO3 > 14%, TCM 0.8–1.2% (0.95), As < 1,800 ppm (optimum < 1,200). Gold Quarry roaster (Table 13-8): SS 1.4–2.5% (2.1), CO3 10–18% (12), TCM 0.4–0.75% (0.6), As < 1,800 ppm, Hg < 25 ppm. Units are weight percent and ppm (FACT, E172).
    • Goldstrike autoclave: alkaline mode needs CO3 > 8% (Table 13-9); acid mode needs SS < 2.8% and CO3 < 8% (Table 13-10); the preg-rob cap depends on the source (E173). Both modes use the same piecewise cubic in grade (opt), with acid recovery about 8.09 points higher (Tables 13-13 and 13-14; FACT, E659). A mode switch costs c_switch·|y_t − y_{t−1}| (DESIGN).
    • Four Corners ore at the roaster (Table 13-16): recovery = (g − T)/g with T = 1.821×10⁻⁵·As + 0.127·g − 4.890×10⁻⁴, g in opt and As in ppm (FACT, E661; the printed formula has an extra parenthesis, E171). Recovered grade 0.873·g − 1.821×10⁻⁵·As + 4.890×10⁻⁴ is affine in (g, As), so it enters the LP exactly as a per-block coefficient, within the fitted range, instead of as an arsenic penalty.
    • Curvature correction (DESIGN). Recovered metal per tonne is f(g) = g·R(g), so E[f(g)] − f(E[g]) ≈ ½ f″(ĝ) σ²_g. The sign follows f″, not the shape of R. For the Goldstrike roaster curve R = 92.03 − 37.36·exp(−12.94·g) (% with g in opt; Table 13-12; FACT, E660), f is convex below about 5.3 g/t and concave above it. Applying R to block-average grades therefore understates recovered metal for low-grade blocks and overstates it for high-grade ones; a curve of the form a − b/g makes f linear and unbiased. fmine-plan evaluates f per realization, or applies the second-order term when only moments exist.
  8. Two process routes, priced separately (FACT plus DESIGN). Pueblo Viejo can send ore to direct POX or to flotation then POX. The TR's pit optimisation assumed the costlier flotation + POX route for every block, a "conservative" case, because short-term plant constraints decide routing (FACT, E265). Route recoveries are in TR §13.3 (Tables 13-4 to 13-6); only flotation + POX costs are published. fmine-plan carries route-split variables x_{s,direct,t} and x_{s,float,t} under the autoclave's sulphur capacity, Σ_s S_s (x_{s,direct,t} + η_S x_{s,float,t}) ≤ Cap_S,t, with η_S the sulphur reporting to concentrate.
    • Flotation + POX variable cost (Table 15-4; FACT, E664): plant −1911.2S⁴ + 857.27S³ − 128.24S² + 11.236S + 6.8302 US$/t and power (794.9833S + 22.3323) kWh/t × P, where S is total sulphur as a fraction (9.04% → 0.0904, never 9.04; G-UNIT-4) and P = US$0.07912/kWh. At S = 0.0904 they give 7.30 + 7.45 = 14.76 US$/t, the Table 15-8 value.
    • Waste costs more to mine than ore (3.68 vs 3.20 US$/t), so the incremental ore mining cost is −0.48 US$/t (Table 15-2): waste goes to a temporary dump and is rehandled, or is co-disposed in the TSF. TSF sustaining capital is 5.96 US$/t for ore and 2.25 for waste (Table 15-5; FACT, E665).
  9. Inter-complex haulage and tolling (DESIGN). In Nevada, Goldrush ore goes to the Goldstrike and Gold Quarry roasters, Cortez refractory ore is trucked about 115 km to Carlin, and Turquoise Ridge ore goes to the Sage autoclave (FACT, E663). The destination index p therefore spans complexes, with haulage cost c^haul_{s→p}(t). Where ownership differs across an arc, a shadow toll τ_{s→p} applies: a 100% Barrick source milled in the 61.5% NGM JV, as Fourmile was until its vend-in (E658; §23.2).
  10. Reagent supply can be a mined stream. Pueblo Viejo's LOM quarries 321,561 kt of limestone against 217,649 kt of pit ore (FACT, E264); it is scheduled here with its own cost and quality model.
  11. TSF capacity is a plan constraint. Kibali's FTSF limits oxide feed until 2028, and a delayed Loulo TSF expansion forced over-height deposition behind a sacrificial buttress (FACT, E218, E219); Goldstrike's storage lasts "through 2028" while a 180 Mm³ TSF is permitted (FACT, E190). Freeboard (§18) supplies the capacity runway and its permitting lead time as a constraint.

Lane's cut-off theory as policy seed and explanation (DESIGN plus FACT).

  • The cut-off grades:
    • Mine-limited: g_m = h / ((p−k)y).
    • Mill-limited: g_h = (h + (f+F)/H) / ((p−k)y), with opportunity cost F = δ·V.
    • Market-limited: g_k = h / ((p − k − (f+F)/K)·y).
    • Balancing cut-offs come from the grade–tonnage curve. The operative cut-off is the median of the three for each capacity pair, iterated on V. This gives a declining cut-off policy (Lane 1964/1988, FACT R7 §5.2).
    • When recovery depends on grade (or on TCM/Au), the cut-off is a fixed point g = cost/(net·R(g)). Turquoise Ridge's 5.66 g/t underground cut-off reproduces only as that fixed point (g = 5.665, R = 79.6%; INFERENCE, E182).
    • Published cut-off reproduction is an M0 check (seven cut-offs: six round to the printed figure, and the Cortez Hills longhole roaster row is 0.1336 against 0.133, within its inputs' rounding; E182–E184). It catches the $/t vs $/st trap: Cortez cut-offs reproduce only with ×0.90718, and with the AB495 tax omitted (E183).
  • Extensions:
    • Material between the marginal and opportunity-cost cut-offs goes to a stockpile when its discounted end-of-life value exceeds the rehandle cost.
    • Under grade uncertainty, classification uses expected loss over the local posterior, not the kriged grade versus cut-off.
  • Consistency check. Lane is the closed-form seed and explanation card, H3e policy search refines it, and the LP is the arbiter. When mine life is endogenous (so time-based fixed cost f and opportunity cost F respond to the plan), the LP's mill-hour dual equals Lane's (f+F)/H term, and PO-PUSH-15 checks this. In a fixed-horizon period LP, f is sunk and the dual reflects only the opportunity cost.

Unit cost consistent with the accounting truth.

  • One aisc(rules_version, inputs) function computes both plan AISC (from plan quantities × CostDriverCard rates) and actual AISC (from FA-certified rows). The full specification is in §21.6.
  • AISC/oz is never the objective. It is a ratio, and high-grading, deferring sustaining capital or reclassifying capital as growth can all lower it while destroying NPV.
  • AISC may enter as a linear constraint, Σ cost_t − A·oz_t ≤ 0. Its shadow price is always published, as "$ of NPV per $/oz of AISC target" (§23.6).

15.7 Grade control: dig lines under uncertainty

  • The information. Grade-control data (blastholes or RC grade-control holes) enters Strata as observations (§13.7). The short-term model is a projection of the belief at T_gc, at SMU support, with realizations.
  • The decision rule (DESIGN). Each material polygon's destination minimizes expected loss over the posterior: E[loss(d, Z)] for d ∈ {mill, leach, stockpile bins, waste}, where the loss matrix comes from the destination economics of §15.6. This is the Verly/Isaaks expected-loss approach (FACT, R7 §6.2), and it replaces "estimated grade ≥ cut-off".
  • Blast movement. Dig lines are shifted by measured or modelled blast movement (§16.3) before classification. Unshifted dig lines are a principal source of ore loss and dilution (HYPOTHESIS; scored at the pilot).
  • Minimum mining width and digability. Polygons respect equipment selectivity (bucket width, bench height), through a morphological constraint on the classified grid.
  • Several live hypotheses (OPEN-STRATA-5). When L1 carries several interpretations with material weight, expected loss is taken over the hypothesis mixture. The DecisionCard shows the destination flip under each hypothesis.
  • Output. Dig lines are recommendations (EFFECT-DIGLINE prepared effects). The grade-control geologist signs them, and they are never pushed to the FMS automatically.

15.8 Schedule compliance as a forecastable, calibrated quantity

Definitions:

  • Spatial compliance: SC_t = (tonnes mined in t from blocks scheduled in t) / (tonnes scheduled in t).
  • Also tracked: sequence compliance, volume compliance, metal compliance, and sequence debt (scheduled but unmined tonnes carried forward, including stripping debt).

Model.

  • k_t ~ BetaBinomial(n_t, α_site, β_site), with a hierarchy over site, pit and horizon.
  • Covariates: fleet availability, plan churn, geotechnical events, blast delays, weather, number of active faces.
  • The prior is wide. The industry figure "as low as 30%" (E026) is a lower anecdote, not a base rate (OPEN-PUSH-2).
  • Each period's forecast is registered (§10) and scored by PIT and coverage, with an eproc drift monitor.

Use in planning.

  • Plans are scored under a compliance kernel K(plan, state), which draws realized extraction with substitution to available adjacent blocks at a grade ratio ρ.
  • A plan that wins only without K is flagged "brittle".
  • Executability features are rewarded: active faces and precedence slack.

15.9 Guards, monitors and proof obligations

Guard (evaluated in order; first match wins) Condition Action
G-PUSH-1 A safety constraint would be priced, or any INV-002 flag (MNPI, safety or sign-off semantics) would be set Refuse and route to a human. No card is emitted.
G-PUSH-2 Bound not verified by fmine-verify No gap is shown; label "heuristic, unbounded"
G-PUSH-3 Optimization gap > 5% Label "heuristic plan"; the word "optimal" is banned from the render
G-PUSH-4 VSS computed with eval_set = opt_set, unpaired draws, or n_eval < 200 Refuse the VSS claim
G-PUSH-5 VSS_oos CI includes 0 The deterministic baseline is the default plan; the stochastic plan is advisory
G-PUSH-6 Calibration ≠ Calibrated Colour ≤ Estimated; refuse the P(target) headline; widen by reference class
G-PUSH-7 AISC forecast from drivers lacking FA certificates Watermark "plan-only metric"
G-PUSH-8 A top-3 sensitivity input has evidence class Assumed Banner: "decision rests on assumption X"
G-PUSH-9 A block's ARD class is unknown and a NAF destination is requested FMINE-REF-402
G-PUSH-10 Schedule references slope angles from a superseded geotech claim Mark the plan Stale; block its use in disclosure

Monitors:

  • M-PUSH-1: ensemble PIT/coverage, on synthetic truth first, then on reconciliation.
  • M-PUSH-2: schedule-compliance e-process.
  • M-PUSH-3: F-factor drift e-process (shared with §20).
  • M-PUSH-4: price-band re-plan trigger.
  • M-PUSH-5: plan churn.
  • M-PUSH-6: CI solver regression on MineLib gaps and times against pinned fixtures.
PO Statement Verification
PO-PUSH-1 The returned pit is a closure (feasible) O(arcs) independent check in fmine-verify
PO-PUSH-2 Max-flow equals min-cut, flow is conserved, no i64 overflow Pre-solve Σ|v| < 2⁶² guard plus flow check
PO-PUSH-3 Nested shells are monotone: λ₁ ≤ λ₂ ⇒ pit(λ₁) ⊆ pit(λ₂) when block values are monotone in λ Property test
PO-PUSH-4 Every dual bound is valid Dual feasibility verified with outward interval rounding, then weak duality
PO-PUSH-5 The schedule is feasible: precedence across periods, capacities Independent checker
PO-PUSH-6 SAA bound CIs achieve nominal coverage Toys with known optimum
PO-PUSH-7 VSS sets are disjoint and paired Type-enforced
PO-PUSH-13 Same inputs and seeds ⇒ same plan digest Replay test across LabRuntime seeds
PO-PUSH-14 Metamorphic laws: price ↑ ⇒ pit ⊇ (for positive-metal blocks); capacity ↑ ⇒ LP value non-decreasing; a duplicated scenario leaves the SAA solution invariant; rescaling money units leaves the plan unchanged Metamorphic suite
PO-PUSH-15 Lane–LP consistency: in a single-mill toy with endogenous mine life, the mill-hour dual equals (f+F)/H Known-answer test

PO-PUSH-8 to PO-PUSH-12 are capital and metric obligations. They are listed under §21.6 and §23.

15.10 Galaxy-brain cards (illustrative values)

GB-13 · Lane's cut-off with a stockpile option.

  • Equation. g_m = h/((p−k)y); g_h = (h + (f+F)/H)/((p−k)y); F = δ·V.
  • Substituted inputs.
    • Price p = $3,000/oz = $96.45/g; k = $6/oz; y = 0.90, so (p−k)y = $86.63/g.
    • h = $22/t; f = $60M/y; H = 10 Mt/y.
    • δ = 8% and V = $2.0B give F = $160M/y.
  • Cut-offs.
    • g_m = 22/86.63 = 0.254 g/t.
    • g_h = (22 + 220/10)/86.63 = 0.508 g/t.
    • Late in life, at V = $0.5B: g_h = (22 + 10)/86.63 = 0.369 g/t.
  • A 0.40 g/t parcel stockpiled for 12 years is worth (0.40·86.63 − 22 − 1.8)·1.08⁻¹² − 0.6 = +$3.7/t. It is stockpiled, not wasted.
  • Intuition. Early in mine life, the opportunity cost of time doubles the mill cut-off. The 0.25–0.51 g/t band is option inventory, not waste.
  • Assumptions. The mill binds (otherwise the balancing cut-off applies); V is iterated from the plan; grades are posterior means, with expected-loss classes applied under uncertainty.
  • Flip. A stockpile recovery loss ≥ 27% (from oxidation) or a price fall of 27% makes the parcel value ≤ its placement cost, and it becomes waste.

GB-14 · Out-of-sample value of the stochastic solution (three-arm, synthetic-truth mine).

  • Equation. VSS_oos = E_B[NPV(x_sto)] − E_B[NPV(x_det)], where B is disjoint from the optimization set A and draws are paired; SE = sd(diff)/√n_B.
  • Calibrated arm.
    • VSS_oos = 1,905 − 1,812 = $93M (5.1%). With sd 110 and n_B = 200, SE = 7.8, so the 95% CI is [78, 108].
    • In-sample on A it was $140M, so the optimizer's optimism is $47M.
    • Against 30 independent truths, VSS is $71M with CI [21, 121].
  • Under-dispersed arm (σ × 0.6): VSS_oos = $12M, CI [−5, 29]. Stochastic value is not demonstrated.
  • Intuition. A third of the in-sample "stochastic value" is optimizer's curse. The rest survives only with calibrated realizations.
  • Assumptions. The generator is representative; S_A = 50; the compliance kernel is off (turned on, VSS_oos falls to $58M).
  • Flip. The truth-arm CI includes 0, or M-PUSH-1 fails. Either demotes the stochastic plan to advisory (G-PUSH-5/6).

GB-15 · The three-gap ledger on one plan.

  • Optimization gap. BZ LP 2,140.0 has a verified bound UB* = 2,140.4. TopoSort plus local search reaches 2,091.0, so gap_opt = 49.4/2,140.4 = 2.31%.
  • Sampling gap. UB_SAA = 1,948 ± 18 (10 batches) and LB_eval = 1,905 ± 8. The sampling gap is 43 ± 20, or 2.2% [1.2, 3.3].
  • Calibration gap. Nominal 90% NPV intervals covered 24 of 30 truths. P(X ≤ 24 | Bin(30, 0.9)) = 0.073, so the status is amber.
  • Intuition. "2.3% from optimal" is a statement about the model. The model is amber-calibrated, so the headline stays Estimated.
  • Flip.
    • Coverage ≤ 22/30 (p < 0.01) → Miscalibrated → widen.
    • gap_opt > 5% → "heuristic plan".

GB-16 · The plan number is not a forecast (schedule compliance).

  • Equation. c ~ beta-binomial posterior predictive; metal = plan·(c + (1−c)·ρ).
  • Substituted inputs.
    • Over 12 months, 2,520 of 4,800 planned blocks were mined as planned (0.525), with a between-month sd of 0.07.
    • So next month's c is 0.53, with 80% PI [0.44, 0.62].
  • Forecast. A plan of 95 koz with substitution grade ratio ρ = 0.82 gives 95·(0.53 + 0.47·0.82) = 87.0 koz [85.4, 88.5]. Past 80% PIs covered 9 of 12 months.
  • Intuition. Execution alone produces a production variance of about 8 koz per month against plan (≈ $36M of revenue timing at $4,500/oz) before any grade uncertainty. Unmined planned blocks are deferred (sequence debt), not lost; their value at stake is the NPV of the deferral plus any sterilization, shown separately.
  • Flip. If ρ → 1 (substitutes are as rich), the metal gap vanishes but sequence debt grows. An M-PUSH-2 alarm resets the prior window.

15.11 Assumptions, gates, kills and open questions

ID Assumption Measured by If false
A-PUSH-1 Ensembles are calibrated at decision support (block, period) M-PUSH-1, coverage tests G-PUSH-6; KILL-PUSH-CAL
A-PUSH-2 kWh/t is additive over blends within ±8% (H-ADD) Plant data Piecewise blend classes
A-PUSH-3 There are few coupling rows per period (BZ-friendly) KILL-PUSH-BZ lag plus aggregation
A-PUSH-4 The compliance kernel is stationary within a quarter M-PUSH-2 Shorter windows; wider intervals
A-PUSH-5 Recovery is per source domain, not per blend Plant reconciliation (§20) Blend-class recovery
Gate / kill Threshold (TARGET) When (months after Pushback start at M4 = month 18; all inside month 36) Deterministic fallback if killed
GATE-PUSH-PIT1 MineLib UPIT exact (integer-scaled) with verified closure +2 months — (must pass)
✖ KILL-PUSH-PIT pitflow within 5× MineFlow wall time on the largest MineLib UPIT, and 10⁷ blocks ≤ 10 min +4 months Bench/panel super-block aggregation, re-verified at fine scale inside the shell. Never a runtime foreign dependency.
✖ KILL-PUSH-BZ PCPSP LP within 1% of the oracle in ≤ 1 h on side-constrained instances +6 months lag bound plus rolling-horizon aggregation; publish the gap
GATE-PUSH-TOPO Gap ≤ 3% on ≥ 80% of PCPSP instances, ≤ 5% on all +6 months Report the honest gap
✖ KILL-PUSH-MILP Blend, fleet and capital subproblems to ≤ 1% within SLA +8 months LP plus rounding with a reported gap; MPS export to the lab
✖ KILL-PUSH-PDLP 1e-4 relative gap on real-size non-closure LPs +9 months BZ/Lagrangian where structure allows; otherwise scenario reduction to sizes fsci handles
✖ GATE-PUSH-STO (K-STO) Calibrated-arm VSS_oos CI excludes 0 and the miscalibrated arms trip M-PUSH-1 before publication +10 months Drop COSMO-scale (b). Keep (a) plus robust overlay plus (e) policy search. Use stochastic methods only for stockpile and cut-off policy.
GATE-PUSH-BLEND HiGHS parity 1e-7; bins vs McCormick ≤ 1% +6 months Piecewise classes
GATE-PUSH-COMP ≥ 24-month hindcast; 80% PI coverage in [0.70, 0.90] Pilot + 6 months Wider prior; label uncalibrated
KILL-PUSH-CAL Ensemble coverage demonstrated on synthetic truth, then on reconciliation Continuous Stochastic outputs stay Estimated and "uncalibrated"; capital decisions use reference-class widening

Open questions.

  • OPEN-PUSH-1. Does UntrustedCandidate import respect the suite's closed-dependency rule? (Owner decision; recommended yes, because no dependency is introduced.)
  • OPEN-PUSH-2. What is the real distribution of schedule compliance across sites?
  • OPEN-PUSH-3. Can aggregation error be bounded provably at 10⁸–10⁹ blocks?
  • OPEN-PUSH-4. How should a client's Deswik/Whittle/COMET plans be ingested as candidates, and which formats?
  • OPEN-PUSH-5. Underground scheduling scale at large sublevel-stoping operations: is ≤ 10⁴ variables enough after aggregation?