Crucible: processing, metallurgical accounting and on-site refining
4,130 words10 subsections5 tablesPlan version 0.1
On this page10
Source: Brenner pass B6 (planning/brenner/B6_operations_plant_tailings_workforce.md, sub-question B6-SQ2),
building on R7 §7, R1 (cards, wear) and the C2–C4 technical-report corpus. Every verdict survived a refuter-first
attempt and a forced third alternative: H6.2b (four-layer versioned CorrelationCards + N-tank RTD
deconvolution fmine-plant::rtd + curvature correction + two-sided stoichiometric blend windows)
and H6.2d (AMIRA P754 check-in/check-out bilinear reconciliation with G-CRUC-6 refusing tautological tonnage MCF)
are adopted over H6.2a (steady-state shift regression, kept only as R0 published-card reproduction mode) and
H6.2c (first-principles population-balance/CFD twin, rejected for v1 on unidentifiability and scale). The crate
is fmine-plant.
17.1 Doctrine
-
The plant is where the subsurface belief meets money. Every block's value depends on a recovery and throughput prediction. Those predictions are the least-validated numbers in most mine plans: recovery is routinely extrapolated beyond the tested range (FACT[U], R7 §7.2).
-
Every process prediction is a card with a validity domain. A prediction outside the validity box is refused (FMINE-REF-203) or explicitly extrapolated with colour
Estimatedand a UU term. -
Recovery and throughput apply at processing support. That is a shift or day blend, declared per circuit, not a block (§13.4). The block-level "recovery" in planning (§15.6) is a domain attribute used under the linearity assumption A-PUSH-5, and the plant reconciliation tests it.
-
Control belongs to the DCS and the plant's advanced process control vendor. Crucible recommends set-points as prepared effects and scores every vendor twin's predictions (§16.5 pattern).
- Example: Metso's Geminex at Lihir was "technically deployed" but not operationally commissioned, with no quantified benefits published; Metso asserts only unquantified energy, water and reagent savings (FACT, E643).
- The industry's believed proof is Freeport's TROI at Bagdad: about +10% throughput and about +1 point copper recovery (FACT[U], consultant-reported by McKinsey in 2020 and seen only second-hand; absent from Freeport's filings; E644).
Crucible's job is to make such claims measurable: registered before, scored after.
17.2 The flowsheet graph (fmine-plant::flowsheet)
- Units. A flowsheet is a typed directed graph of unit operations, versioned with valid time (plant
modifications are supersessions). Unit types:
- crushers and HPGR;
- SAG, AG and ball mills;
- cyclones and screens;
- gravity concentrators (centrifugal, spirals, shaking tables);
- flotation banks and columns;
- thickeners and filters;
- leach tanks; CIL/CIP trains; elution; electrowinning cells; induction or tilting furnaces;
- heap leach pads with ADR plants;
- autoclaves (POX), roasters, BIOX reactors;
- SX mixer-settlers and EW tank houses;
- Merrill–Crowe;
- tailings pumping;
- water recovery.
- Streams. Each stream carries:
- The same graph serves three purposes:
17.3 Process models as cards
Every model below follows frankensim's CorrelationCard pattern (Pattern, §13.9). Each card has inputs with units,
a validity box, fitted parameters with a covariance, the fitting dataset's evidence references, and a colour.
| Process | Model family | Card inputs | Notes and doctrine |
|---|---|---|---|
| Crushing and grinding energy | Bond's law, W = 10·Wi·(1/√P80 − 1/√F80) kWh/t (FACT[U], R7 §7.1); SMC/Morrell specific energy for AG/SAG; JK drop-weight A×b, ta | Hardness at processing support (additive proxy, §13.4), F80, target P80, circuit configuration | Wi depends on closing screen and feed preparation (FACT, R7 §7.1). Throughput = installed power × utilization ÷ specific energy, with hardness variability as the main driver. |
| Fragmentation → SAG throughput | Mine-to-mill card on ROM x50/x80 and fines fraction (§16.3) | Fragmentation observations | HYPOTHESIS per site; the card is fitted only after registered forecasts are scored |
| Classification | Efficiency-curve models (e.g. Plitt-type corrected partition curves) | Cyclone geometry, pressure, solids % | — |
| Gravity (Au) | GRG (gravity-recoverable gold) test-based recovery | GRG tests on composites | Gravity also reduces the coarse-gold nugget problem in downstream sampling (FACT[U], R7 §7.4) |
| Gravity (Sn) | Size-by-size recovery curves for cassiterite, with heavy fines and slimes losses | PSD and liberation by size class | Tin recovery is strongly size-dependent (FACT, R7 §7.5, Angadi et al. 2015), so the Sn card is coupled to the comminution card, never evaluated alone |
| Flotation (Cu, Ag, Au in sulphides) | First-order R(t) = R∞(1 − e^(−kt)) with a distribution of k (rectangular/Klimpel or gamma); grade–recovery frontier | Mineralogy (CuS speciation, pyrite), grind, reagents, residence time | FACT (R7 §7.3): 71% of rectangular-model R∞ estimates fell below the measured 32-minute recovery. The rate-distribution choice changes extrapolation, so every card records it, and model choice is a ModellingDecision. |
| Cyanide leach and CIL/CIP | Leach kinetics (shrinking-core or empirical); carbon adsorption isotherms and kinetics; cyanide and lime consumption | Head grade, gravity tail, PRI and TOC (§13.6), grind, sulphide content, cyanide-soluble Cu | Preg-robbing is the classic surprise. The PRI(TOC) card feeds recovery per realization. CIL mitigates mild preg-robbing; strongly preg-robbing carbonaceous ores need roasting, pressure oxidation with thiosulphate leaching, or blanking agents (FACT[U], R7 §7.4), so the route itself is a decision variable. NGM measures preg-robbing as a percentage from a spike test, with source-specific feed caps (< 40% or < 60%; FACT, E173, E175); the same organic carbon gives 0–40% or 75–100% by source, confirmed by Raman, so the card takes an optional carbon_type covariate (E175). A TCM threshold is scoped to its use: TCM > 1% was waste for one test-sample selection yet is capped feed (< 120,000 t/y) at the Sage mill (C2 §4.3e). Goldstrike's calcium thiosulphate RIL circuit was converted to CIL in Q1 2023 for $30M (FACT, E174); no demo text presents it as running thiosulphate after that date. |
| Heap leach | Recovery-vs-time curve per ore type and crush size, R(t) = R∞(1 − e^(−kt)) with column-to-field scale-up factors; solution application rate; lift schedule | Column tests, crush size, clay content, agglomeration | Scale-up from columns to the field is the dominant uncertainty and is explicit (GB-20). Heap inventory is a latent state (§20.8). Book convention (FACT, Veladero 2013–2017; E275, E276): sites carry heap WIP as a recoverable-basis roll-forward, Inv_t = Inv_{t−1} + Σ T·g·R_card − produced, with R_card a fixed grade/ore-type formula. The card exposes R_card (book) and R∞ (posterior) as separate named parameters, and the inventory's MetalStage is Recoverable (§25.2). |
| Refractory gold: POX, roasting, BIOX | Sulphide oxidation extent → downstream CIL recovery; oxygen and acid balance; As fixation | S²⁻, As, carbonate, organic C | No independent head-to-head review exists, only site comparisons (FACT, R7 §7.4). Cards are site-specific and Estimated until reconciled. |
| Copper oxide/secondary leach and SX-EW | Heap or dump leach curves; SX extraction and stripping stages (McCabe–Thiele on isotherms); EW mass by Faraday's law, m = I·t·M/(n·F) × current efficiency | CuAS/CuT ratios (§13.6), acid consumption (gangue), PLS grade | Cathode output is a check-out measurement with high precision, which makes it a strong reconciliation anchor |
| Silver | Flotation concentrate payables or cyanidation (Merrill–Crowe or carbon) | Ag mineralogy | Silver is mostly a by-product; its payable terms dominate its value (FACT, R7 §7.5) |
| Thickening, filtration, tailings rheology | Settling flux and yield stress cards | Clay mineralogy, PSD | frankensim LBM has no Bingham or Herschel–Bulkley rheology (FACT, R1). These are correlation cards until upstream adds them. |
Validity enforcement (DESIGN). A plan whose feed blend leaves a card's validity box (hardness, grind, PRI or clay outside the tested range) is published with the out-of-domain claim highlighted in red and its UU term priced as a flip margin (§9.3). Example: "Recovery falls below the plan's break-even if preg-rob > 60% in the Q3 blend; testwork covers only < 40% for this source."
Card layers (DESIGN; C4 P8). A recovery card has four layers, each versioned:
- the test-work card with its validity box;
- named stage operational factors, attested (Pueblo Viejo business plans apply them on top of test-work cards; FACT, E256);
- caps and correction factors as explicit parameters (Zaldívar caps insoluble-Cu recovery at 55%, cutting average recovery by about 9%; FACT, E290);
- the route assumed for reserves, as a
ModellingDecision(Pueblo Viejo assumes the costlier flotation+POX route for all ore; FACT, E265).
- The Cu heap/dump card is speciation-weighted, TCu_rec = F1·ASCu/TCu + F2·CNCu/TCu + F3·SCu/TCu, with residence time in the validity box (Zaldívar F1/F2/F3 = 96/78/40; E289). It is not an R(t) curve.
- If Pushback or Hallmark use a recovery other than Crucible's current card, the statement shows the divergence. Porgera's recovery equations "are not used" in its cut-off or reserve models (FACT, E295).
- Versions are real and mixed. One Turquoise Ridge reserve statement uses three intercepts of the same surface card (100.79, 97.14, 101.79), plus a +3% plant adjustment (FACT, E181). Every Reserve element cites its card version.
- Unit-aware ingestion. One company publishes three unit conventions for its cards (g/t converted inside the
formula by ×0.029167; oz/st; g/t with fractions labelled "%"), and one printed formula has unbalanced
parentheses (FACT, E171).
CorrelationCardgainsinput_units,output_scaleandparse_check. G-UNIT refuses a card whose inputs mix units, and an import gate evaluates every card at three reference grades against the published LOM average. - Fitting hygiene and residence time (
fmine-plant::rtd; FACT plus DESIGN). The Goldstrike roaster curve was fitted on 12-hour shifts, dropping shifts below 90% availability and their neighbours "to avoid upset plant conditions and false CIL retention times" (FACT, E170). Leach trains hold a day or more of inventory: the Cortez Pipeline CIL's nominal retention is 36–48 h (FACT, E663), and the Carlin TR gives no hours. Shift-paired head and tail assays therefore misstate recovery whenever feed grade moves.fmine-plant::rtdmodels a leach train as N stirred tanks in series with bypass fraction α and dead-volume fraction β: h(τ) = α δ(τ) + (1 − α) (N/τ̄) (Nτ/τ̄)^{N−1} e^{−Nτ/τ̄} / (N − 1)!, with τ̄ = (1 − β) V / Q. When the slurry flow Q(t) varies (the < 90% availability shifts), the convolution runs in throughput-volume coordinates ∫Q dt rather than clock time, because the kernel is then time-varying. Convolving feed tonnes and grade with h tracks gold in circuit and removes the hold-up bias from fitted cards and from shift and daily balances (§20.4; GB-41). - A ready calibration demo. Turquoise Ridge registers 71 monthly lab-vs-plant pairs (2008–2014): plant minus bottle-roll mean +2.35 points, SD 4.49, with 17 lots above +5 (FACT, E177). It is a public dataset for the first recovery-forecast calibration card (§10).
17.4 The geometallurgical chain, end to end
- Strata (§13.6) holds the spatial fields: grades, hardness proxies, PRI and TOC, CuAS/CuT, S, As, clay, density.
- Pushback (§15.6) chooses blends at processing support.
- Crucible predicts throughput, recovery, reagent use and concentrate quality for the blend, per realization, and registers the shift/day/month forecast (§10).
- Touchstone (§20) reconciles actual plant performance and scores the forecast. Residuals update card parameters (with an InvestigationCase when a surprise monitor fires, §10.5) and Strata's geomet field bias priors.
Sampling density (OPEN-STRATA-8). The minimum geometallurgical sampling density at which transfer cards beat domain averages is an OPEN question. Crucible measures it on the pilot by comparing registered forecasts made with cards against forecasts made with domain averages.
Geomet coverage report. For each metallurgical domain, Crucible lists which percentile bands of Strata's
SMU-support distribution of each primary variable are covered by tested samples. The target is every 5th
percentile; with fewer than ten samples, at least the 5th, 25th, 50th, 75th and 95th (E389). Cards evaluated
outside the covered bands render OutsideValidity. This turns OPEN-STRATA-8 into a measurable gap before the
forecast comparison runs.
17.5 Metallurgical accounting (AMIRA P754 discipline)
Principles adopted (FACT, R7 §7.6). The AMIRA P754 Code of Practice for Metal Accounting requires:
- unbiased and precise accounting;
- check-in/check-out measurement;
- a stated precision for every mass, sampling and assay stream;
- data reconciliation;
- stocktakes;
- competent-person sign-off and independent audits;
- separation of primary (whole-plant) and secondary (circuit) accounting.
Implementation (DESIGN).
- Data reconciliation. Weighted least squares or Bayesian reconciliation over the plant subgraph, using the measurement-error covariances of §12.5. It is run by the same engine as mine-to-mill reconciliation (§20.3), so plant and mine numbers never disagree by construction.
- Gross-error detection. A global χ² test, per-measurement tests and an
eprocdrift monitor per sampler and weightometer. A failed test opens an InvestigationCase. Measurements are never silently dropped. - Stocktakes cover gold in circuit (carbon inventory, solution and tank inventory, clean-up results) and concentrate stockpiles. A stocktake is a measurement with an error model and resets the latent-state uncertainty.
- Attestation. The metallurgical accountant signs the monthly metal balance (
AttestedInterpretationpattern). FrankenMining supplies the reconciliation certificate (§20.9) and never signs. - Precision targets. Per-stream precision is policy data, set by the site's P754 assessment. The system reports achieved precision against target, and the gap is a VOI candidate (§20.6).
- Check-in and check-out stay separate. MCF (in) and MCF (out) are both exposed; their gap is the plant's unaccounted gain (Kibali 2025: check-out 2.6% above check-in; FACT, E210). A tonnage MCF that uses the same flowmeter tonnes as plant feed cannot detect flowmeter bias (Loulo; C3 §3.12), and the report says so.
- Capacity is two numbers. Nameplate and demonstrated capacity are stored separately (Kibali: design 7.2, target 8.2, peak 8.5 Mtpa; E239).
- Assurance inputs. A site that applies P754 "without necessarily going through formal training" (Loulo; C3 §3.12) has that recorded as an input to metal-accounting assurance scoring, not as a finding against people.
17.6 On-site refining and product custody
| Product | Process chain | Custody evidence | Accounting hand-off (§21) |
|---|---|---|---|
| Gold/silver doré | Electrowinning sludge or Merrill–Crowe precipitate → calcining → smelting → bars | Bar weight, fire assay of bar samples (top/bottom drill or pin), seal numbers, vault records, shipment manifests; dual-control sign-offs | Doré inventory (oz Au, oz Ag) → shipment → refinery outturn (refined oz credited, typically after weeks) → settlement. Outturn vs mine assay differences are reconciled as a measurement node with bias tracking. |
| Copper concentrate | Flotation → thickening → filtration → stockpile → shipment | Draft survey or weighbridge, moisture determination, assay exchange, umpire, splitting limits | Provisional invoice at shipment; quotational-period price adjustments; final invoice after assay exchange. Under IFRS 9 the provisionally priced receivable is measured at FVTPL as a whole (no bifurcation); under US GAAP (ASC 815) the embedded derivative is bifurcated. Bullion computes the fair-value change per the book's policy and FA posts it. |
| Copper cathode | SX-EW | Cathode weights, LME grade sampling | Sales at shipment or warehouse warrant |
| Tin concentrate | Gravity → upgrade → shipment | As for copper concentrate; Sn assay methods are distinct measurands (§13.6) | Smelter terms (payable Sn, deductions, penalties) |
Safety-semantic refusal FMINE-REF-403 (concentrate shipment).
- Concentrates can liquefy at sea above their transportable moisture limit (TML) under the IMSBC Code.
- If the moisture determination is missing, stale or above TML at the declared confidence, FrankenMining does not produce a "ready to ship" status.
- The release is a human act with a certificate.
Security. Bullion and doré custody records are a high-assurance lane:
- dual attestation with HumanAuthorityToken (§31.3);
- an append-only seal and vault log;
- discrepancies above tolerance opening an InvestigationCase with restricted visibility.
17.7 Reagents, consumables and wear
- Consumption models. Cyanide, lime, xanthates and other collectors, frothers, flocculant, acid (SX-EW and
POX) and oxygen. Each is a card with feed-dependent inputs (sulphides, cyanide-soluble Cu, acid-consuming
gangue). Consumption feeds
CostDriverCards (§21.6). - Cyanide custody. The cyanide lifecycle follows the International Cyanide Management Code: purchase, transport, storage, use, WAD-CN at the tailings discharge, decommissioning. Discharge criteria are policy data. FrankenMining records the evidence state and never asserts code compliance.
- Hazardous by-products. Mercury from retorting is a
HazardousByproduct(Hg)material with custody records. Veladero stores flasked mercury on site and its removal "is not in the Closure Plan" (FACT, E285); the closure completeness check (§18.6) maps every stored hazardous inventory to an ARO line. - Grinding media and liners.
- Media consumption (kg/t) and liner wear use Archard-type cards (§16.5) with abrasion-index inputs from Strata.
- Measured liner profiles from scanners are observations, and liner change-out timing is a DecisionCard priced at the mill-hour dual.
- Process alternatives are
CapitalCandidates (§23).- Examples: glycine leach (Draslovka has piloted it with Barrick, and its February 2026 alliance with Avathon targets leach recovery and reagent use; FACT, B5 W3), HPGR retrofits, flotation column additions, coarse particle flotation.
- Each needs testwork evidence with a validity box. A candidate without testwork has evidence class
Assumedand triggers guard G-PUSH-8's banner.
17.8 Plant optimization: what Crucible recommends
- Throughput vs recovery. Grind modes, flotation residence time and leach residence time are traded at the dual prices from Pushback (§15.6). Crucible supplies the (Q, ΔR) frontiers (GB-19).
- Blend set-points per shift. Crucible recommends the feed blend within bands, based on the forecast hardness, PRI and deleterious elements of the available stockpile bins and faces. These are prepared effects (§31.3).
- Campaigning. Refractory ore campaigns versus blending, priced by the LP.
- No closed-loop control. Plant MPC and expert systems belong to the DCS. Crucible scores their stated benefits.
17.9 Guards, proof obligations, gates and kills
| Guard | Condition | Action |
|---|---|---|
| G-CRUC-1 | Card evaluated outside its validity box | FMINE-REF-203, or explicit extrapolation with colour Estimated and a priced UU term |
| G-CRUC-2 | Recovery applied at block support | FMINE-REF-102 (support mismatch); must use processing support |
| G-CRUC-3 | Metal balance closes only with an unexplained adjustment | FMINE-REF-101 (no plug); open an InvestigationCase |
| G-CRUC-4 | Concentrate moisture missing, stale or above TML | FMINE-REF-403 |
| G-CRUC-5 | A vendor-twin benefit claim with no registered pre-period forecast | Rendered as an Assertion (§7.1), not a measured benefit |
| G-CRUC-6 | A tonnage MCF or check-in/check-out balance uses the same flowmeter/weightometer stream as both numerator and denominator (Loulo; C3 §3.12) | Refuse precision claim (TautologicalTonnageMcf); watermark "cannot detect flowmeter bias" |
| PO | Statement | Verification |
|---|---|---|
| PO-CRUC-1 | Flowsheet mass balance conserves solids, water and each element at every node | Property tests on generated flowsheets |
| PO-CRUC-2 | Data reconciliation is unbiased with the stated covariance on synthetic flowsheets with known true flows | Monte Carlo known-answer test (R7 §7.6 test design) |
| PO-CRUC-3 | Gross errors of stated size are detected at stated power and false-alarm rate | Simulation |
| PO-CRUC-4 | Bond and Faraday cards reproduce textbook worked examples exactly | Known answers |
| PO-CRUC-5 | Size-by-size Sn recovery conserves mass across size classes | Property test |
| Gate / kill | Threshold (TARGET) | Fallback |
|---|---|---|
| GATE-CRUC-01 | Pilot plant: 12 months of monthly metallurgical balances reproduced from raw measurements with reconciled values within stated precision; gross-error detection live | Secondary accounting only; flag |
| GATE-CRUC-02 | Registered monthly recovery and throughput forecasts for 12 months; 80% interval coverage in [0.70, 0.90], pooled over both quantities (n = 24: P(pass ∣ 0.8) ≈ 0.80, P(pass ∣ 0.6) ≈ 0.19 before autocorrelation; 12 outcomes alone pass a calibrated forecaster 52% of the time, R7-C120). The twelfth outcome resolves 12 months after plant data first flows (GATE-DATA-03) | Cards stay Estimated; planning uses reference-class widening |
| GATE-CRUC-03 | Heap inventory posterior (where a heap exists) narrows as leach-curve data accrue, and P(inventory < book) is reported monthly to Bullion. Known answer: the Veladero 2013–2017 roll-forward reproduces the published leach-pad inventory to ±1 oz (E275) | Point inventory with a documented NRV sensitivity |
| ✖ KILL-CRUC-1 | Plant historian or lab data not accessible by month 9 of a site engagement (§34.4) | Crucible limited to the monthly metallurgical report as an attested observation |
17.10 Galaxy-brain cards (illustrative values)
GB-19 · Push tonnes or chase recovery? (copper flotation concentrator)
- Equation.
- Q = P/W with W = 10·Wi·(1/√P80 − 1/√F80).
- Value per hour V = Q·(g·R·net − c_var).
- Substituted.
- Wi = 15 kWh/t, F80 = 2,000 µm and ball-mill power P = 16.8 MW.
- At P80 = 106 µm: W = 11.22 kWh/t and Q = 1,498 t/h.
- At P80 = 150 µm: W = 8.89 kWh/t and Q = 1,889 t/h (+26%).
- Recovery 90% → 87%; g = 0.5% Cu; net $8,000/t payable Cu; c_var = $6/t.
- Result.
- Fine grind: V = $44,939/h. Coarse grind: $54,405/h, which is +$9,466/h, or about $76M/y at 8,059 operating hours.
- The break-even coarse recovery is 74.5%.
- But if the mine cannot deliver the extra ore (mine-limited), coarsening simply loses 3 points of recovery: −$1,798/h.
- Intuition. The right grind is a property of which constraint binds, not of the plant alone. That is exactly what the LP's mill-hour and ore-supply duals say.
- Assumptions. Ball-mill-limited circuit; flotation residence time and tailings capacity absorb +26%; Bond's law holds over the range.
- Flip. The ore-supply dual is zero (mine-limited) → fine grind. Flotation residence time binds → recovery falls faster than 3 points → re-solve.
GB-20 · How much gold is really on the heap?
- Equation.
- Remaining recoverable = T·g·R∞ − recovered to date, with R∞ uncertain from column-to-field scale-up.
- Leach-curve observations R(t) = R∞(1 − e^(−kt)) narrow R∞ over time.
- The site's book is Σ T·g·R_card − recovered, a recoverable-basis roll-forward (FACT, E275). The latent is Σ T·g·R∞ − recovered − solution and channelling losses. The card reports Δ = latent − book with its interval.
- Substituted.
- 20 Mt stacked at 0.6 g/t is 385,809 oz contained.
- R∞ = 70% ± 8% (1σ) gives 270,066 ± 30,865 oz recoverable.
- 200,000 oz have been recovered, so remaining inventory = 70,066 oz, 80% interval [30,510, 109,622].
- Intuition.
- The balance sheet carries one number. The truth is a distribution three times wider than its centre suggests.
- The cost per recoverable ounce, and therefore the NRV test (IAS 2), depend on R∞.
- Assumptions. A declared, possibly skewed, scale-up prior (normal here only for illustration); no solution-inventory or channelling effects; no grade bias in placed ounces. Production shortfalls under a regulatory restriction enter the book as inventory automatically: in Veladero's 2017 cyanide-restriction year the book rose 83,900 oz (+33%) while production ran 21.9% below budget (FACT, E278). The restriction is therefore a covariate. The physical tail can also sit above the book: about 0.5 Moz of residual leach was excluded from Veladero's reserves (FACT, E279).
- Flip. P10 inventory < ounces implied by the carrying cost at the long-term price → Bullion prepares an NRV
Workpaperfor human review (§21.5). Six more months of lift-level leach curves halve σ (HYPOTHESIS, tested on the pilot heap).
GB-41 · Shift-paired recovery vs. residence-time deconvolution.
- Equation. Shift-paired recovery is R̂_k = 1 − g_tail,k / g_feed,k. The tails actually leave on the convolved feed (h ∗ g_feed)(t), with h the N-tank kernel of §17.3.
- Substituted (illustrative: N = 8, τ̄ = 24 h, true recovery 88% at every grade; feed 3.0 g/t except one 12 h
shift at 9.0 g/t):
- an impulse leaves within 12 h with probability 1 − Σ_{j=0}^{7} 4^j e^{−4}/j! = 0.051, and 86% of it leaves between 12 h and 36 h;
- mean tail grades in the four shifts from the pulse: 0.366, 0.549, 0.714 and 0.504 g/t;
- shift pairing reports 95.9% for the high-grade shift (+7.9 points), then 81.7%, 76.2% and 83.2% (−6.3, −11.8 and −4.8 points). A regression of R̂ on feed grade invents a steep grade–recovery slope where true recovery is flat.
- Intuition. Same-shift pairing ignores a day of inventory in the tanks. Deconvolving by h recovers 88% in every shift, including slow shifts where Q drops and τ̄ stretches.
- Assumptions. Known tank volume, a slurry flowmeter, and tracer-calibrated α and β.
- Flip. At monthly aggregation (Δt ≫ τ̄) with stable month-end inventory the boundary effect is small, and steady-state cards suffice.
Open questions.
- OPEN-CRUC-1. Which plant historian and LIMS exports the pilot site permits.
- OPEN-CRUC-2. Whether the site's P754 assessment exists and what its precision targets are.
- OPEN-CRUC-3. Whether refinery outturn data (refiner statements) can be ingested electronically.
- OPEN-CRUC-4. How to express vendor-twin predictions (Geminex, MetOptima) as registrable forecasts.