34.1 Gate semantics

  • A gate passes only with a recorded measurement against its threshold: the measured value, the anchor, the certificate and the date (§0.2). Targets are not results.
  • A ✖ kill gate names its fallback in advance. When it fires, the fallback ships and the plan says so. A kill gate is never quietly re-scoped.
  • Gate records live in the decision ledger (CELL-DEC) as typed entries, so the program's own decisions are auditable in the same way as the mine's.

34.2 Admission gates (foundations)

Gate Foundation Pass criteria Section
INT-AS-001 asupersync 0.5.0 The nine admission criteria below (from FSS-DD §2.9); one asupersync package id per posture §27.5
INT-AS-SEC-001 asupersync 0.5.0 Mitigation tests for defects S3(a)–(d) §31.4
INT-ATP-001 ATP QUIC/TLS only; chunk-receipt resume without the 0.6.0 journal; lab partition matrix green §26.7, §31.4
INT-FA-001 franken_accounting FA-ACC-01…13 green at the pinned FA revision §21.3
INT-FSQL-001 frankensqlite The ten admission criteria below (from FSS-DD §3.10), in the projection role; R-tree bbox p99 ≤ 50 ms over 10⁷ intervals §27.4
INT-FGDB-001 frankengraphdb Projection only; certified replay; measured benefit on 3 named queries (else KILL-2) §27.4
INT-FSEARCH-001 frankensearch quill + hash/model2vec only; no ort/fastembed; wall-scoped indexes §27.4
INT-FNX-001 franken_networkx Scale benchmark on synthetic precedence graphs §27.4
INT-FMCP-001 fastmcp Parity gate; confined to fmine-mcp §30.3
INT-FTUI-001 frankentui asupersync lane; inline mode; no write verbs outside the registry §30.3
INT-FMD-001 franken_markdown Library rendering; deterministic by digest §30.5
INT-FMERM-001 frankenmermaid Default features; no HiGHS or C toolchain in the closure §30.5
INT-FSIM-001 frankensim Separate-clone spike; one-package-id result recorded (expected FAIL today) §27.1
INT-NUM-001 frankenscipy, frankenpandas (not fp-io), franken_numpy (fnp-io), frankenjax (fj-core, fj-lax, fj-ad) Closures pass L-5 and the one-package-id rule; default features off; oracle parity on every consumed kernel; cross-ISA determinism scope recorded §27.3

What makes an admission record valid (R7-C017, R7-C083, R7-C101, R7-C153). An INT-* record is valid only if it cites a commit in which Cargo.lock is tracked and contains the foundation, with the cargo-deny and one-package-id output for that lock committed beside it (CI run ids alone expire after the retention period). A record written before the foundation is in the graph is a pre-admission desk check and says NOT_APPLICABLE or PENDING, never PASS. INT-AS-001 is split: INT-AS-001a (closure checks: one package id, criterion 9, [patch.crates-io] single Cx) stays in WP-00 and reads NOT_APPLICABLE while asupersync is absent; INT-AS-001b (criteria 1–8) runs in WP-05 at M1 and depends on the residency planner (BD-107), a wall-test bead and a named criterion-8 bead (BD-337). INT-NUM-001 likewise records the FD-row fallback (own kernels in fmine-numerics) until a foundation crate enters the closure.

INT-AS-001 criteria (inlined from FSS-DD §2.9). Integration is admitted only when:

  1. the same end-to-end scenario passes under production and lab time;
  2. no owned work survives region close;
  3. every non-trivial drain emits a progress certificate;
  4. every obligation reaches a terminal or an explicit indeterminate state;
  5. capability narrowing is tested statically and dynamically (here: check-caps plus the runtime-mask lab test, §31.4);
  6. routing cannot cross unauthorized site, venture or MNPI scopes;
  7. ATP corruption, truncation, reordering, path-failure, resume and repair campaigns preserve root integrity;
  8. scheduler or diagnostic adaptation cannot alter authoritative results;
  9. no second runtime, detached worker or ambient timer appears in the dependency closure.

INT-FSQL-001 criteria (inlined from FSS-DD §3.10). fsqlite is a projection here (single writer, rebuildable), so criteria 2, 6 and 9 apply only if BEGIN CONCURRENT is used, which FrankenMining does not plan:

  1. a single-threaded reference implementation of each projection;
  2. schedule exploration over concurrent reads and projection writes;
  3. crash injection at every reserve/materialize/publish boundary;
  4. positive and negative-read phantom tests;
  5. deterministic semantic-rebase equivalence;
  6. commit-combiner sequence and active-registration proofs;
  7. stale-anchor refusal and historical AS OF replay;
  8. recovery that distinguishes published, staged, aborted and indeterminate states;
  9. witness-refinement exhaustion creates false conflicts only;
  10. no direct use of lower-level APIs that bypass the connection and witness pipeline.

34.3 Convergence and kill gates by subsystem

Subsystem Convergence gates Kill gates (✖, fallback in the section) Section Earliest
Plumb GATE-PLUMB-E1…E5 KILL-PLUMB-5 (executive card test), KILL-PLUMB-6 (false alarms) §9, §10 M1
Lodestar GATE-LODE-P1…P6 KILL-LODE-1…4 §11 M4
Corebox GATE-CORE-01, -02 — §12 M2
Strata GATE-STRATA-G0…G5 G0, G3, G5 carry kill fallbacks §13 M3 + n
Highwall GATE-HIGH-01…03 KILL-HIGH-1, -2 §14 M5
Pushback GATE-PUSH-PIT1, -TOPO, -BLEND, -COMP, -STO KILL-PUSH-PIT, -BZ, -MILP, -PDLP, -CAL §15 Starts M4 (month 18); PIT1 by month 20; acceptance M6
Headframe GATE-HEAD-01…03 KILL-HEAD-1 (no FMS export by month 9) §16 M5
Crucible GATE-CRUC-01…03 KILL-CRUC-1 (no plant data by month 9) §17 M2
Freeboard GATE-FREE-01…03 KILL-FREE-1 §18 M5
Muster GATE-MUST-01…03 — §19 M5
Touchstone GATE-TOUCH-01…06 GATE-TOUCH-02 (bias recovery), GATE-TOUCH-04 (material finding) §20 M1–M2
Bullion GATE-BULL-01…03; GATE-POST-01 (3 sites × 3 months of synthetic close through fad: 0 duplicates, every month fa replay-identical, every Workpaper ≤ 128 rows) GATE-BULL-01 (public reproduction), KILL-1 (FA scale) §21 M0 (M3 for GATE-POST-01)
Helm GATE-HELM-01, -02; GATE-CAP-04, -05 — §22, §23 M1
Hallmark GATE-HALL-01…03 GATE-HALL-02 (independent QP replay) §24 M0–M1
Units, time, CRS PO-UNIT/CRS/TIME (§25.6) — §25 M0
Bedrock GATE-STORE-01, GATE-SYNC-01/02, GATE-INGEST-01, GATE-BM-01 KILL-4 (ledger persistence), KILL-5 (telemetry rate) §26 M1
Suite GATE-FSIM-DRIFT, GATE-FSIM-RECONV, GATE-PIN-06 KILL-2 (fgdb), KILL-3 (frankensim) §27, §31.4 M1
Workspace GATE-LAYERS-00, GATE-BUDGET (§28.4) — §28 Commit 1
Numerics GATE-DET-01 — §29 M1
Adit GATE-ROBOT-01, GATE-REPORT-01 — §30 M1, M3
Security GATE-WALL-01, GATE-SEC-01 — §31 M1, before M2
Portal GATE-PORT-01, -02 KILL-6 (OMF purity) §32 M1–M2
Testpit GATE-ORACLE-01, GATE-GEN-01, GATE-E2E-01 — §33 Commit 1–M1

34.4 Data-acquisition gates

The best model without data access is a demo (§0.7). These gates measure access itself, and each has a fallback that keeps delivering value without data (B5 M2′).

Gate Threshold Deadline Fallback if missed
GATE-DATA-01 Agreement Signed data agreement, named data steward and site sponsor, insider list and blackout policy in force; the issuer's public lane frozen and its state change recorded in BD-200 (§31.1; R7-C137); README's "not affiliated" wording updated Month 4 Escalate once through the executive sponsor, then M2′ planning
GATE-DATA-02 Security IT security review passed for the on-prem binary (SBOM, threat model, no egress) Month 5 (GATE-SEC-01) Offer the review pack to a delivery partner (F15)
GATE-DATA-03 First snapshot Grade-led threshold: 8–12 historical quarters of reconciliation inputs (block and GC models, dispatch tonnages, surveys, mill sampler, metallurgical balance, cost-centre extracts) imported with explained rejections (GATE-PORT-02). Recovery-led threshold (Lumwana): the §37.3 recovery set imported with explained rejections; either threshold meets the gate (R7-C084, R7-C102) Month 7 M2′: parent-level metric and reserve assurance on public data, the Nevada exploration hindcast and PQ-7 deal cards
GATE-DATA-04 Operations data FMS cycle export (KILL-HEAD-1) and plant historian/LIMS export (KILL-CRUC-1) Month 9 of a site engagement Headframe and Crucible limited to survey epochs, monthly reports and certified activity drivers
GATE-DATA-05 Personal data Privacy impact assessment and works-council review completed before person-level ingest (GATE-MUST-03) Before Muster at any site Aggregate-only workforce analytics
GATE-DATA-06 Exploration effort Effort data (drilling, geophysics, geochemistry coverage) with licence for one public district (OPEN-LODE-1) Month 15 (M4) Tract-mode exploration with Manski bounds (KILL-LODE-2)

The assumption that matters most. Whether site data arrives by month 7 is this plan's largest scheduling assumption. The plan does not rely on it, because M2′ delivers without site data. It is a planning input, never a forecast of anyone's decision. Three steps must all finish in time (INFERENCE, E599):

  • an executive and a Lumwana site sponsor committed, with the data list accepted, by month 4;
  • the agreement, insider list and blackout in force by month 4–5;
  • the security review passed and 8–12 quarters imported by month 7.

The fastest Barrick precedent, Avathon, went from first collaboration (December 2025) to software at selected U.S. sites in Q2 2026, inside the North American perimeter (FACT[secondary], E591). It is a benchmark for pace, not a forecast for FrankenMining. The alternates follow Lumwana in this order: North Mara/Bulyanhulu, Kibali, then NGM and Pueblo Viejo.

The wedge choice is unchanged: it is the only option that is useful without site data and decisive with it, and H-f leads at every p in GB-38 (§37.2). What changes is planning weight: M2′ is fully planned and is resourced from M1, not held in reserve. Pursuing the alternates in parallel adds little, because they share the executive sponsor and the corporate security review (R7-C126). Planning weight moves only on observable signals (W4 §6.5): a named Lumwana site sponsor by month 2, a security questionnaire issued within 30 days, or one sample month of the reconciliation pack by month 4 moves it towards M2; no site sponsor by month 3 moves it towards M2′; no draft agreement at GATE-DATA-01 triggers M2′.

34.5 The program gate (month 12)

If neither M2 nor M2′ yields an executive-recognised use, the program is re-scoped before any M3 spending.

  • An executive-recognised use is a FrankenMining number or card cited in a guidance, capital or reserve meeting minute, or the sponsor's written equivalent.
  • This is the "stop when the bottleneck has shifted" rule applied to the program itself.