EV matrices and the galaxy-brain card index
1,260 words2 subsections2 tablesPlan version 0.1
D.1 Math-family EV matrix (alien-artifact selection)
Score = (Impact × Confidence) ÷ Effort, each 1–5. Families below 2.0 were rejected or deferred.
| Family | Where it compiles to artifacts | Impact | Conf. | Effort | Score | Decision |
|---|---|---|---|---|---|---|
| Bayesian decision theory with loss matrices | DecisionCards, destination classification (GB-22), VOI | 5 | 5 | 2 | 12.5 | Core |
| Proper scoring and calibration ledgers | Forecast ledger, calibration flags (§10) | 5 | 5 | 2 | 12.5 | Core |
| Data reconciliation (WLS, gross-error tests) | Touchstone joint estimation (§20) | 5 | 5 | 3 | 8.3 | Core |
| Anytime-valid sequential tests (e-processes, CUSUM) | Surprise monitors, QA/QC drift (§10, §12) | 4 | 5 | 2 | 10.0 | Core |
| Geostatistics and change of support | Strata parity and simulation (§13) | 5 | 4 | 4 | 5.0 | Core |
| Network flow and LP duality | Pit limits, schedules, Lane duals (§15) | 5 | 5 | 4 | 6.3 | Core |
| Stochastic programming (SAA, VSS) | Three-gap certificate, GB-14 | 4 | 3 | 4 | 3.0 | Gated (GATE-PUSH-STO) |
| Point processes (thinned LGCP) | Lodestar regional model (§11) | 4 | 3 | 4 | 3.0 | Adopted at M4 |
| Bayesian search theory | Dry-hole updates (GB-02) | 3 | 5 | 1 | 15.0 | Adopted |
| Submodular selection | Drill-target portfolios (§11) | 3 | 4 | 2 | 6.0 | Adopted, guarantees scoped |
| CVaR / distributionally robust choice | Capital programme, irreversible actions | 4 | 4 | 3 | 5.3 | Adopted |
| Real options (staged) | Earn-ins, study gates (§23) | 4 | 4 | 3 | 5.3 | Adopted |
| Index decompositions (LMDI) | AISC waterfalls (GB-26) | 4 | 5 | 1 | 20.0 | Adopted |
| Queueing and max-plus algebra | Fleet bounds, AHS token locks, FA posting capacity (GB-17, GB-28, GB-40) | 4 | 5 | 2 | 10.0 | Adopted |
| Residence-time deconvolution and curvature correction | fmine-plant::rtd N-tank convolution, recovery curvature correction (§15.6, §17.3, GB-41) |
5 | 5 | 2 | 12.5 | Adopted |
| FoS pore-pressure sensitivity and pore-pressure ratio B̄ | Real-time VWP-to-FoS propagation, contractive TSF raise TARP (§14.5, §18.3, GB-42) | 5 | 4 | 2 | 10.0 | Adopted |
| Beta-binomial / e-process anti-Goodhart verification audit | CCV tick-and-flick suppression detection (G-MUST-6, §19.5, GB-43) |
4 | 5 | 1 | 20.0 | Adopted |
| Merkle/MMR and CRDT-free single writers | Ledger, sync certificates (§26) | 5 | 5 | 3 | 8.3 | Core |
| Gittins indices / bandit regret bounds | Exploration budgets | 2 | 1 | 3 | 0.7 | Rejected (§23.1) |
| Credal sets / Dempster–Shafer as stored belief | Epistemic core | 2 | 2 | 3 | 1.3 | Rejected (§9.2) |
| Pixel ML as prospectivity of record | Lodestar | 2 | 2 | 2 | 1.0 | Rejected (§11.2) |
D.2 Galaxy-brain card index
Every card states the equation, substituted values, intuition, assumptions and what would flip it. Arithmetic was recomputed by the domain audit (Appendix H). † = corrected by the domain audit; ‡ = amended with corpus evidence (Appendix I).
| Card | § | Title | Revised |
|---|---|---|---|
| GB-01 | 11.9 | The discovery-thinning integral | |
| GB-02 | 11.9 | Bayesian search after three dry holes | |
| GB-03 | 9.6 | Plug-in vs posterior P(≥1) | |
| GB-04 | 11.9 | EVOI of an IP survey before a six-hole program | |
| GB-05 | 11.9 | Heavy-tailed marks: never value with the median | |
| GB-07 | 11.9 | Analogue transfer and partial pooling | |
| GB-08 | 10.4 | Anytime-valid coverage alarm | |
| GB-09 | 11.9 | Novel deposit-type mass via Good–Turing | |
| GB-10 | 13.5 | Store or regenerate realizations? | |
| GB-11 | 13.1 | Why the kriged model cannot be the authority (conditional bias; slope of regression) | † ‡ |
| GB-12 | 13.5 | Common random numbers make "did the new drilling change the decision?" answerable | |
| GB-13 | 15.10 | Lane's cut-off with a stockpile option | |
| GB-14 | 15.10 | Out-of-sample value of the stochastic solution | |
| GB-15 | 15.10 | The three-gap ledger on one plan | |
| GB-16 | 15.10 | The plan number is not a forecast (schedule compliance) | † |
| GB-17 | 16.11 | How many trucks per shovel? Match factor vs queueing | |
| GB-18 | 16.11 | What is blast-movement monitoring worth on one ore blast? | |
| GB-19 | 17.10 | Push tonnes or chase recovery? (copper flotation) | |
| GB-20 | 17.10 | How much gold is really on the heap? | ‡ |
| GB-21 | 18.8 | Freeboard exceedance under climate shift (and what a pump buys) | |
| GB-22 | 18.8 | Point-estimate NAF that should be treated as PAG | † ‡ |
| GB-23 | 19.9 | FIFO 14/7 vs 8/6: cheaper per seat, but hours and fatigue are not for sale | † |
| GB-24 | 20.12 | One month of tonnes, reconciled | |
| GB-25 | 20.12 | Whose fault is the missing 9.5%? | |
| GB-26 | 21.9 | An exact, order-independent AISC waterfall | ‡ |
| GB-27 | 21.9 | GEO moves when the gold price moves | ‡ |
| GB-28 | 21.7 | Why monthly summaries, quantified (FA posting capacity) | |
| GB-29 | 22.8 | Should we buy metallurgical testwork before the final investment decision? | |
| GB-30 | 23.10 | CVaR capital allocation, and why the buyback is not a hurdle rate | |
| GB-31 | 23.10 | A junior's market price implies 93% conversion of inferred ounces | † |
| GB-32 | 23.10 | The reference-class capex prior needs a blowout regime | |
| GB-33 | 24.10 | The "±15% at 90% over a quarter" heuristic turns on one correlation | ‡ |
| GB-34 | 25.7 | A constant moisture assumption manufactures a "mill problem" | |
| GB-35 | 26.13 | Telemetry: fgdb as authority fails by arithmetic | |
| GB-36 | 26.13 | Sync over satellite, and why Merkle diffs are a checked null | |
| GB-37 | 29.8 | One ulp is harmless to a decision and fatal to a digest | |
| GB-38 | 37.2 | The wedge under data-access uncertainty | |
| GB-39 | 14.6 | A section that passes on FoS can fail on PoF once pore pressure is uncertain | ‡ |
| GB-40 | 16.11 | AHS intersection tokens vs. staffed haulage (Carlin's planned 40-truck autonomous fleet) | B6 |
| GB-41 | 17.10 | Shift-paired recovery vs. residence-time deconvolution | B6 |
| GB-42 | 18.8 | Pore-pressure ratio B̄ vs. a drained assumption on a contractive TSF raise | B6 |
| GB-43 | 19.9 | CCV completion vs. a random audit: when "0 non-conformances in 300 checks" signals suppression | B6 |
GB-06 was retired before publication; its capex-mixture content is GB-32, and references were redirected.