Risks and the pre-mortem
1,825 words2 subsections2 tablesPlan version 0.1
On this page2
35.1 Pre-mortem: "It is 2029 and FrankenMining failed at Barrick. Why?"
Source: B5 §7. The stories are ordered roughly by likelihood × impact (HYPOTHESIS). Each gives a leading indicator visible by about month 6 and a countermeasure already designed into this plan.
| # | Failure story | Leading indicator | Countermeasure in this plan | Residual |
|---|---|---|---|---|
| F1 | An incumbent AI platform absorbed the space. FrankenMining was seen as overlapping with the AI operating layer already in place and was not taken forward. | The evaluation is folded into the existing AI-platform programme; "how is this different from the AI platform?" | Position as the evidence substrate agents cite (§32.3); pilot outside NA; offer no computer-vision, maintenance or supply-chain agents (NONGOAL-005) | High |
| F2 | Data never arrived. Security review of an unknown pure-Rust vendor took 9 months. | No signed agreement or data steward by month 4 | Security pack at M0; on-prem single binary; public and synthetic lanes deliver with no data (§34.4) | Medium |
| F3 | MNPI breach or lane contamination. A forecast leaked, or someone traded in a blackout. | No insider list; lanes share a machine | Two physically separate lanes; private-access people never author public forecasts; insider list and blackout for the whole team (§31.1) | Low probability, fatal impact |
| F4 | QPs refused, and legal agreed. Probabilistic metrics read as automation of judgment and as discoverable contradictions. | QP declines attestations; legal asks to remove intervals | Never classify; the CP act makes the QP the author; no_claim lines; co-design with the Head of MRM from M1; counsel designs retention and privilege (§24) |
Medium |
| F5 | The site ignored it. A senior geologist's spreadsheet stayed the recon of record. | After 3 shadow months, the old pack still rules | Parity first: reproduce the site's own pack exactly; the site geologist is the named author; reduced pack time is the benefit; embed a person on site (§20) | Medium |
| F6 | Yet another dashboard. Executives said "interesting" and changed nothing. | No executive reuses a number in a meeting | The unit of delivery is a DecisionCard plus a scored forecast; the program gate (§34.5) | Medium |
| F7 | Overclaimed probabilities. A "90%" interval missed 4 of 8 quarters in front of the CFO (P = 0.005 if it were calibrated: strong evidence of miscalibration, R7-C118). | Coverage below nominal; intervals narrower than reference classes | Default uncalibrated; track record beside every forecast; UU budgets; refuse decision-grade probabilities without calibration (§9, §10) |
Medium |
| F8 | The value was not there. The pilot site already reconciled well. | Attribution matches the site's commentary by month 9 | Pre-select a site with recorded variance; report the null honestly; allow one second site (§37) | Medium |
| F9 | The suite never converged. 30–40% of time went to sibling fixes. | > 20% of hours on sibling repos | Dependency firewall; lift with provenance; FA through the CLI; no deliverable depends on a sibling (§27) | Low–medium |
| F10 | Purity cost the year. Rebuilding parsers, CRS and samplers ate M0–M1. | M0 slips > 4 weeks; infrastructure > 40% of LOC | A wedge with minimal missing primitives; foreign tools as oracles; budget protocol (§28.4) | Medium |
| F11 | Key-person risk on both sides. One relationship, one architect; changes of role at the client. | One person answers every question; the sponsor moves | Named counterparts in several roles (CFO, Head of MRM, a site GM); plan-first documentation; DecisionCards make reasoning transferable | High for a small team |
| F12 | The IPO took priority. The NA carve-out drew on the same finance, IT and MRM teams. | Repeated deferrals; perimeter changes | Stay off the IPO critical path; pilot in the remaining-parent perimeter | Medium |
| F13 | JV partner conflict. Operating data became dispute evidence (cf. the NGM 2026 default notice, E034). | Legal asks about partner consent | Pilot at a 100%-owned site; partner outputs only through governed channels (§31.2) | Low once the site is chosen |
| F14 | OEM lock-in. Exports dropped fields or became paid services. | Exports need vendor professional services | OMF v2 from day one; snapshot importers; flat-file fallbacks; never require write or real-time APIs (§32) | Medium (real-time); low (monthly) |
| F15 | Procurement and vendor viability. A tiny shop failed onboarding. | Requests for references and SOC 2 | A delivery or assurance partner as the contracting wrapper; source escrow; a support runbook | Medium |
| F16 | Scale broke trust. 10⁸–10⁹ blocks and 100–1,000 realizations overwhelmed the stack at M5–M6. | The pilot's mined-volume subset takes hours to load | The wedge needs only mined SMUs per period (10⁵–10⁶); regenerate, don't store; benchmarks before claims (§13.5, §26) | Deferred, not removed |
35.2 Risk register
| ID | Risk | Severity | Mitigation | Owner |
|---|---|---|---|---|
| RISK-01 | Overlap with an incumbent AI platform (F1) | High | §32.3 contract; pilot outside NA | Owner + sponsor |
| RISK-02 | Data access (F2) | High | §34.4 gates; M2′ | Sponsor |
| RISK-03 | MNPI breach (F3) | Fatal impact | §31.1 | Counsel + owner |
| RISK-04 | QP and legal rejection (F4) | Medium | §24 doctrine; counsel review (OPEN-HALL-4) | Head of MRM |
| RISK-05 | Site non-adoption (F5) | Medium | Parity first; embedded engineer | Site GM |
| RISK-06 | Dashboard syndrome (F6) | Medium | DecisionCards; program gate | Owner |
| RISK-07 | Overclaimed probabilities (F7) | Medium | Calibration ledger; uncalibrated default |
Head of MRM |
| RISK-08 | Checked null at the pilot (F8) | Medium | Site selection; second site | Sponsor |
| RISK-09 | Suite non-convergence (F9) | Low–medium | §27 firewall | Owner |
| RISK-10 | Purity cost (F10) | Medium | §28.4; oracles | Owner |
| RISK-11 | Key persons (F11) | High | Multi-threading; documentation | Owner |
| RISK-12 | IPO calendar (F12) | Medium | Off the critical path | Sponsor |
| RISK-13 | JV dispute exposure (F13) | Low | 100%-owned pilot | Counsel |
| RISK-14 | OEM export lock-in (F14) | Medium | Snapshot importers; data-ownership clauses | Sponsor |
| RISK-15 | Procurement (F15) | Medium | Delivery partner; escrow | Owner |
| RISK-16 | Scale (F16) | Deferred | Benchmarks; regeneration | Owner |
| RISK-17 | Licence rider (MIT + OpenAI/Anthropic) on lifted code, the substrate and FrankenMining's own LICENSE (E681) in a client-facing product. The rider reaches anyone acting on behalf of, for the benefit of or under the direction of OpenAI or Anthropic, and bars making the software available to or for them, so the decision also covers agents hosted by those parties reading through fmine-mcp or the CLI (§30.4) |
OPEN | Owner and counsel decision before M2, and before the M2 agent slice opens | Owner + counsel |
| RISK-18 | asupersync 0.5.0 security and durability defects (B4 S3) | High | §31.4 mitigations; GATE-PIN-06 | Owner |
| RISK-19 | Human review is the FA posting bottleneck (GB-28) | Medium | Monthly trunk; delegated reviewer ask (OPEN-BULL-3) | Controller |
| RISK-20 | Name collisions (fm, fmd, fm-*) |
Medium | fmine- prefix (OPEN-B4-09) |
Owner |
| RISK-21 | Residency statutes misread: 39 of 72 researched rows are INFERENCE (W3) | High | Fail-closed default; each row carries status, confidence and review_by; counsel on the W3 §7 clauses before any regional node (OPEN-B4-01) |
Counsel |
| RISK-22 | Goodhart: a metric used in pay can drift from the quantity it measures (AISC deferral, CCV completion) | Medium | KPI price list (§23.6); deferral detection (GB-26); CCV quality, not counts (§19) | Owner |
| RISK-23 | Code changes (JORC 2026, the NI 43-101 replacement) shift disclosure requirements mid-build | Medium | Renderers as registry rows (§24); OPEN-HALL-2 | Head of MRM |
| RISK-24 | Evidence state misread as a safety statement (TSF, slopes) | High impact | Four false flags; "evidence state, never safe" wording; no geotechnical_signoff (§18) |
Tailings function |
| RISK-25 | LOC overrun repeats FTX (2.7×) | High (sibling velocity reference class, §28.3; R7-C115) | §28.4 protocol from commit 1 | Owner |
| RISK-26 | Host-state action at a demonstration site: suspension, provisional administration, retroactive code, tenure lapse (Loulo-Gounkoto 2025: suspended, loss of control, no Q1–Q3 2025 data, then settlement and retroactive 2023-Code royalties for 2024–2025; E248, E412; Kibali permits 2029/2030 vs LOM 2043, with renewal under Art. 80 requiring +5% State equity; E245, E444) | High | Site-quarter state NOT_PUBLISHED; CountryRegime as-of dating (§23.4); G-HALL-6 tenure flags; GATE-BULL-01 excludes NOT_PUBLISHED by name; no silent fill |
Owner + counsel |
| RISK-27 | Water-use conflict in a hyper-arid, state-equity project: community and institutional groundwater concerns (E330–E333) | High | G-FREE-7/9; groundwater DATA-GATE (§18.4); evidence state, never "no impact" | Head of Environment |
| RISK-28 | Security provided by state forces at a state-equity project (E342) | Medium | VPSHR commitment set as registry data; human-rights grievance escalation tracked as OB-COMMIT |
Counsel + Sustainability |
| RISK-29 | Unapproved revisions (E304) ingested as evidence | Medium | DocApproval on every DocLocator; draft-sourced cells cap at conflicted/stale |
Owner |
| RISK-30 | Demo text misstates a site fact taken from a superseded filing (e.g. Goldstrike's thiosulphate circuit, converted to CIL in 2023; E174) | Medium | Every demo claim cites a dated source; sources older than the latest filing are flagged | Owner |
| RISK-31 | Issuer data terms: Barrick's site terms allow copying only for non-commercial, personal or educational use of unmodified material; committed derived workbooks or values may need approval (R7-C052, R7-C158, R7-C160) | Medium | Locators, URLs, sha256 and computed results only until decided; synthetic or fetch-at-test fixtures; seek IR's written approval | Owner + counsel, before the next code push |
| RISK-32 | A synthetic, stand-in or mislabelled figure reaches an issuer reader as the issuer's own (the unpushed M0 slice did this; Appendix K.2) | High impact | Registered inputs only, typed refusal on any missing file, synthetic printed on fixture output, filed-page check by a second person, and an executable uncited-number check with a seeded negative control (§21.6) |
Owner |
| RISK-33 | Process records overstate: beads closed with a generic reason, integration records marked PASS for crates not in the build (R7-C013–R7-C018) | High | Close reasons name the bead's own test, gate record or decision entry; INT records cite a tracked Cargo.lock containing the foundation and its cargo-deny output (§34.2); an xtask check rejects generic reasons | Owner |