Audit fold-in
2,068 words7 subsections3 tablesPlan version 0.1
On this page7
H.1 ProcessH.2 Domain-accuracy audit: 15 findings, all folded inH.3 Suite-fit audit: 30 claims checked, 11 problems, all folded inH.4 Consistency audit: 15 findings, all folded inH.5 Corpus passH.5b Second-wave review, corpus second read, and corrections to the concurrent revisionH.6 Open audit items
H.1 Process
- MOR case file (
planning/mor/MOR_CASE.md): a neutral decision contract, E001–E033 and pivotal questions PQ-1 to PQ-7, built before any design argument. - Brenner passes B1–B6 answered the pivotal questions across all eleven engines (Appendix B;
planning/brenner/B1…B6). - Fresh-eyes audits (2026-10-28; reports in
planning/mor/audits/AUDIT_1…AUDIT_3): three independent read-only reviewers who did not write the plan checked domain accuracy, suite fit (against the sibling repos' code at their pinned revisions) and internal consistency. - Corpus pass (2026-10-28): six read-only agents over the supplied documents (Appendix I), then a second-reader
audit of the corpus rows and the quarterly workbooks (
planning/mor/audits/AUDIT_4_corpus_claim_verification.md). - Public-source research pass and second-wave review (2026-10-29): five primary-source research agents
(
planning/research/W1…W5, Appendix J) and a review of equations, guards and the bead graph (planning/mor/audits/AUDIT_5_second_wave_review.md). - Second-reader checks of the concurrent revision (2026-10-29): two primary-source agents re-read every new FACT claim, and the new mathematics was checked numerically (Appendix H.5b).
H.2 Domain-accuracy audit: 15 findings, all folded in
| # | Finding | Disposition |
|---|---|---|
| 1 | LUC misnamed; the slope ≈ 0.1 case presented as general; "conditional bias goes unreported" | Fixed: Localised Uniform Conditioning; single-case stress case; GB-11 range b = 0.8/0.5/0.1; later strengthened by the corpus (b ≈ ρ; correlation and cut-off tonnage in the flip) |
| 2 | Newmont AISC example mixed guidance and actuals | Fixed: Q3 2026 by-product $1,454/oz vs co-product $1,963/oz |
| 3 | JORC 2026 reconciliation labelled FACT | Fixed: exposure-draft content, wording and commencement unverified |
| 4 | IFRS 9 provisional pricing described as a bifurcated embedded derivative | Fixed: FVTPL as a whole under IFRS 9; bifurcation under US GAAP |
| 5 | CIL called the standard response to preg-robbing | Fixed: CIL for mild; roasting, POX with thiosulphate, or blanking for strong |
| 6 | Kuz-Ram exponent 19/20 | Fixed: 19/30 |
| 7 | GB-22 flip impossible as stated | Fixed: sulphur precision dominates; S sd ≤ 0.15% with ANC sd ≤ 4 gives P(PAG) 0.038 |
| 8 | GB-31 branch NAVs inconsistent with stated P_dev | Fixed: per-branch P_dev 0.80/0.55 restored from B3 |
| 9 | GB-23 saving mostly the salary assumption | Fixed: equal-hourly case ($53k/seat, ≈ $21M/y) shown beside the headline |
| 10 | M2 alternate site contradicts the 100%-owned preference | Fixed: Twiga 16% governance stated |
| 11 | NRV at the long-term price for all inventory | Fixed: per-inventory-class price basis |
| 12 | GB-16 counted deferred metal as lost | Fixed: production variance; deferral valued separately |
| 13 | Q1 2026 AISC rise attributed to royalties alone | Fixed: royalties and corporate G&A |
| 14 | "Most reconciliation failures are basis failures" unsupported | Fixed: "many", labelled HYPOTHESIS |
| 15 | LP dual and greedy-guarantee statements too strong | Fixed: endogenous mine life; guarantees scoped to the monotone coverage term |
Checked and sound: the arithmetic of the 28 cards the report lists, the cited formulas, planning algorithms, GISTM and TML facts, accounting standards and the Barrick and industry figures (to be re-verified against primary filings before executive presentation).
H.3 Suite-fit audit: 30 claims checked, 11 problems, all folded in
| # | Problem | Disposition |
|---|---|---|
| 1 | The chrono/time ban could never pass (transitive through fsqlite, fastmcp, frankenpandas, asupersync tls) |
Fixed: the ban applies to direct dependencies and public APIs, with a per-foundation allow-list (L-5) |
| 2 | fastmcp =0.5.0 brings asupersync 0.4.5 |
Fixed: =0.13.0 |
| 3 | ftui 0.7.x brings asupersync 0.4.9 | Fixed: =0.9.0 |
| 4 | fnx pin contradicted itself; preflow_push absent at fgdb's pin |
Fixed: fnx at 9d710b1c; the oracle runs in a dev workspace; FD-FGDB-01 |
| 5 | "frankenjax without fj-ffi" unsatisfiable through fj-api |
Fixed: consume fj-core, fj-lax, fj-ad; FD-FJ-05 |
| 6 | franken-evidence/-decision in S0 broke the layer and serde rules | Fixed: S0 schema types; fmine-decide is the single adapter; CELL-DEC rows use S0 types |
| 7 | OPEN-SUITE-1, -2, -4 resolvable | Closed: APIs exist; Philox variants differ (golden vectors); fp-io excluded (KILL-6 path) |
| 8 | asupersync pin labelled as an fgdb revision | Fixed |
| 9 | S3(c) described as fixed in 0.6.0 | Fixed: unchanged in 0.6.0; first-party-only rule persists; FD-AS-01 |
| 10 | fsci "no preconditioned CG/MINRES" overstated | Fixed: ILU-preconditioned pcg; unpreconditioned MINRES; FD-FSCI-01 |
| 11 | Minor: winding lift imports, UFuncArray sidecar, fgdb Point index scope, FA HEAD | Fixed |
H.4 Consistency audit: 15 findings, all folded in
| # | Finding | Disposition |
|---|---|---|
| 1 | M0–M2 deliverables without crates; phase-A crates without phase-A work | Fixed: fmine-decide to phase A (BD-225–227 into WP-02); fmine-metalacct and fmine-fa-bridge to phase B; phases now 35/18/6 crates, 615/392/121k |
| 2 | Pushback start M4 vs M6 | Fixed: starts M4 (month 18), acceptance M6; fmine-optimize and fmine-lp to phase B; all relative gates inside month 36 |
| 3 | §38 dependencies contradicted the bead graph (cycles) | Fixed: beads relocated (BD-080, -097, -098, -125); §38's column is generated from the bead graph and the WP graph is acyclic |
| 4 | KILL-1 defined twice | Fixed: one definition in §21.3 with two triggers; §37.3 cites it |
| 5 | Early gates without closing beads | Fixed: BD-257–BD-270 (INT-AS-001, GATE-WALL-01, GATE-PLUMB-E3, KILL-PLUMB-5/6, INT-FSEARCH-001, GATE-CRUC-02/03, GATE-REPORT-01, INT-FNX-001, GATE-SYNC-02, GATE-STRATA-G3/G5, the M6 stochastic LOM) |
| 6 | Gate milestone conflicts; Strata months collided with milestone ids | Fixed: GATE-SYNC-02 at M5; GATE-HALL-02 = GATE-STRATA-G5 in WP-16; Strata months written S+n |
| 7 | GB-31 numbers | Fixed (with H.2 #8) |
| 8 | Identifier defects (G-CAP, GATE-PUSH-BZ, KILL-PROS-1, OPEN-STRATA-3/4, GB-06, RISK-B4-10, PO-HIGH) | Fixed: GATE-CAP-01…03; KILL-PUSH-BZ; KILL-LODE-1; OPEN-STRATA-4; GB-32; RISK-16; PO-HIGH-1…6 added |
| 9 | Seven cross-references to the wrong subsection | Fixed |
| 10 | Layer rules vs fmine-sync/fmine-telemetry IO |
Fixed: S1 may do ledger, CAS, telemetry and sync IO; V does all other IO |
| 11 | OPEN-item rule not met by section-level items | Fixed: inheritance rule in §36.3; missing rows added |
| 12 | K-layer ceiling sum | Fixed: 514; total 1,298 |
| 13 | Underground equipment and Highwall obligations thin | Fixed: underground development cycle, longhole/ring blasting, backfill, LHD, hoisting, dozing/ripping/scraping and demolition (§16.3–16.4); Highwall guards, PO-HIGH-1…6 and GB-39 (§14.6) |
| 14 | External criteria and ids not self-contained | Fixed: INT-AS-001 and INT-FSQL-001 criteria inlined; E023 references replaced by INV-002 |
| 15 | Minor contradictions and label collisions | Fixed: E001–E035; FTX overran its plan; CONTRACT.md ten sections; label scope note in §0.3; refusal code 201 |
H.5 Corpus pass
84 proposed plan changes: 75 accepted in full, 8 in part, 1 validation only; 111 in-place edits; beads BD-271 to BD-307. Details, declined items and data gates are in Appendix I.
Appendix cross-check. Writing these appendices against the body found two more defects, both fixed:
- M0 coverage was overstated. "2025Q1–2026Q2" read as six contiguous quarters, but the two workbooks hold 2025Q1, 2025Q2, 2026Q1 and 2026Q2 plus both half-years (period headers re-read from the xlsx). 2025Q3 and 2025Q4 joined the data gate (§21.6, §37.3; E148 correction appended in the case file).
- The consumed numerics foundations had no admission gate, although §27 requires one for every consumed foundation. INT-NUM-001 (§34.2) and BD-308 were added, and BD-041 (the first production use of fsci-stats) now depends on it.
H.5b Second-wave review, corpus second read, and corrections to the concurrent revision
- AUDIT_5 (
planning/mor/audits/AUDIT_5_second_wave_review.md, 2026-10-29) reviewed the plan after BD-309–BD-320 and W1–W5 and folded in: guard tables for G-CORE-1/2 (§12.6) and G-STRATA-11; FMINE-REF-108 and FMINE-REF-504 in §25.6 and §31.3; PO-LODE-15 naming; BD-309 edges into BD-161 and BD-312 (533 edges, 0 cycles);fmine-timein §28.3; and the B6 fold-in. Its two primary-source items in §15.6 were themselves wrong and are corrected below: the "Carlin exponential 0.8926·[1 − exp(−22.2995·(Au − 0.032))]" and "Cortez rational cubic 1.1536 − 0.0046/g − …" roaster laws appear in no corpus document (E154 and E181 are unrelated rows), acid POX recovery is not linear, and the Table 15-8 check works at S = 0.0904, not 0.0368. - AUDIT_4 (
planning/mor/audits/AUDIT_4_corpus_claim_verification.md) re-read E101–E399 and the 18 quarterly workbooks: 273 exact, 18 confirmed with nuance and 3 page-locator fixes (E146, E211, E212; the MOR_CASE note of the same day lists E124, E134 and E239 by mistake). It also found two hidden external-link sheets in the Q1 and Q2 2026 AISC workbooks holding 154#REF!cells. - Second-reader checks of the concurrent revision (2026-10-29). Two primary-source agents re-read every new FACT
claim against the PDFs and workbooks, and the new mathematics was checked numerically. Corrections, with new
evidence E656–E672:
- Fourmile: FM24-200D is 1.3 m @ 16.25 g/t, and the 30.6 g/t interval in FM24-209D is 1.6 m inside 16.3 m @ 47.07 g/t (not 28.0 m and 57.9 m). "30–37 km of drilling" and the "Birch–Dorothy corridor" are not in the deck, FM25-260DW1 is on p. 8, and since 9 Aug 2026 Fourmile is to be vended into NGM (E656–E658).
- Carlin: the roaster curve is 92.03 − 37.36·exp(−12.94·g) with g in opt; both POX modes share one cubic, acid about 8.09 points higher; the Gold Quarry window is Table 13-8; the TR says nothing about autonomy (E659–E662).
- Autonomous haulage: Cortez finished 23 retrofits in May 2026 for a Q3 2026 rollout, and Carlin's 40 started in Q2 2026 for operations in Q1 2027 (E619). Nothing was "deployed 2023–2025", and ore moves by truck, not rail (E663).
- Pueblo Viejo: Tables 15-2 and 15-3 are mining and fixed costs, not a route comparison; 281.7 and 352.1 kt are the 2025 opening and closing plant-cone inventories in an MCF reconciliation, not capacities; waste costs more because of rehandling and co-disposal, not sub-aqueous placement (E664–E667).
- Lumwana and Kibali: the 12% → 9% loss figures, the 68 km line, the 27 Mtpa baseline and the "330 kV STATCOM" are not in the deck (330 kV is the line voltage; the STATCOMs are at neighbouring mines). Kibali's diesel bank is 32 MW, not 36, and no 50% diesel cut is attributed to solar and BESS (E668, E669).
- Loulo-Gounkoto: TCC $1,897/oz and AISC $2,240/oz are Q2 2026; H1 2026 is $1,906/oz and $2,104/oz (E670).
- Mathematics: the dispersion score of
SpatialFrontPitwas not centred (mean −0.075 under the null, which breaks Ville's bound), and its detection times were optimistic (a 1.4× variance excess needs about 220 polygons, not 15–30). The FoS sensitivity omitted the implicit dependence of m_α on F (10–14% low). GB-41's shift tails, GB-40's second-lane wait and GB-43's interval were recomputed. The curvature correction's sign follows (gR)″, which changes sign near 5.3 g/t on the Carlin curve. The "tree-knapsack matroid" with a Lagrangian dual is replaced by bundle greedy with a valid data-dependent upper bound, and the soft-contact blend now keeps unit variance.
H.6 Open audit items
- H-1. External review rounds (planning-workflow: at least four rounds by a strong reasoning model until the
diff is marginal). Round 1 (
AUDIT_1–AUDIT_3) and round 2 (AUDIT_5) are folded in; at least two remain. - H-2 (done 2026-10-29). Brenner pass B6 for Headframe, Crucible, Freeboard and Muster (§36.4;
planning/brenner/B6_operations_plant_tailings_workforce.md), folded into §16–§19, Appendix B and Appendix D. - H-3 (done 2026-10-29; Appendix J). Primary-source verification of the Barrick and industry figures used in Part I: 72 claims, 49 verified, 2 corrected, 15 partly right, 4 secondary-only, 2 unverifiable (W5). Porgera 2020, Cobre Panamá 2023 and the Mali 2023 Code now rest on primary sources (W2). Residual FACT[U]: the Panama sentencia number and Gazette issue numbers, the Mali implementing-decree number and the Porgera FSA rates.
- H-4 (partly done).
AUDIT_4re-read E101–E399 and the quarterly workbooks. The research rows E401–E655 still need a second reader, andAUDIT_4itself deserves a sampled third read, becauseAUDIT_5's own primary-source "verifications" introduced errors (H.5b). - H-5 (done 2026-10-29). The 320 plan beads and 533 dependency edges of §39 are instantiated in
.beads/(br), andbr dep cyclesreports no cycles. The idea-wizard and beads-workflow polishing rounds remain. Round 7 added BD-321 to BD-357 to §39 (357 beads, 589 edges, 0 cycles); they are not yet in.beads/, and BD-323 corrects the closed beads there before any new bead is created (Appendix K).