Glossary
1,362 words1 tablePlan version 0.1
Domain terms are defined as this plan uses them. Where industry usage varies by site, the plan treats the definition as registry data (for example F-factors, §20.4), and this glossary gives the default.
| Term | Meaning in this plan |
|---|---|
| AIC | All-in costs (WGC 2013/2018): AISC plus non-sustaining capital and other growth costs (§21.6) |
| AISC | All-in sustaining costs (WGC): cost of sales components, sustaining capital, G&A, exploration and reclamation for current operations, per ounce sold, with a by-product or co-product basis (§21.6) |
| Anchor | An immutable, content-addressed publication point of the authority ledger. Every published number cites one (§26) |
| ARD / PAG / NAF | Acid rock drainage; potentially acid-forming; non-acid-forming. NAPP = 30.6·S − ANC (kg H₂SO₄/t); NPR = ANC/MPA (§18.5, GB-22) |
| ARO | Asset retirement obligation: the closure provision under IAS 37 / ASC 410-20 (§18.6, §21) |
| Attestation | A signed human act (CP, QP, EoR, controller, ITRB). It changes a Claim's authority field, never its evidence class (NL-3). Software never attests (INV-002) |
| Basis | The declared accounting of a quantity: wet/dry, 100%/attributable, contained/recoverable/recovered, metal stage, by-/co-product (§25) |
| Bead (BD-) | One unit of planned work, mapped one-to-one onto a br issue (§39) |
| Bench / berm / inter-ramp | Open-pit slope geometry at increasing scale; acceptance criteria differ by scale and consequence (§14.2) |
| BZ | Bienstock–Zuckerberg decomposition for precedence-constrained production scheduling LPs (§15) |
| CAS | Content-addressed storage: 4 MiB chunks, fanout-16 Merkle manifests, root published last (§26) |
| CCV | Critical-control verification (ICMM critical control management) (§19) |
| CIL / CIP | Carbon-in-leach / carbon-in-pulp gold recovery (§17.3) |
| Claim | The universal output object: value, support, basis, evidence class, calibration flag, UU term and provenance (§8) |
| CP / QP | Competent Person (JORC) / Qualified Person (NI 43-101, S-K 1300). Signs disclosure; software prepares support only (§24) |
| CRM | Certified reference material inserted into assay batches (§12.4) |
| CRN | Common random numbers: the same realization index across alternatives, so differences are not sampling noise (§9.5, GB-12) |
| Cut-off grade | The grade separating destinations; Lane's three limiting cut-offs (mine, mill, market) and their balancing grades (§15.6) |
| DecisionCard | The only executive output format: recommendation, distribution, evidence classes, flip margins, VOI and the human decision recorded (§22) |
| Declared estimator | The QP's estimator (e.g. ordinary kriging) reproduced bit-for-bit as Estimator::DeclaredOk, a projection beside the belief ledger (§13.1) |
| Desurvey | Converting collar plus downhole survey into 3-D interval positions (§12.2) |
| Dilution / ore loss | Waste included in ore, and ore sent to waste, at mining (§15.7, §16.3) |
| e-process | An anytime-valid test statistic (supermartingale under the null); alarms can be checked continuously without inflating error (§10.4, §12.4) |
| Evidence class | How something is known: Measured, Derived, ModelledCalibrated, ModelledUncalibrated, Elicited, Transferred{aoa}, Assumed, Assertion (§7.1). Attestation is not an evidence class |
| EVSI / VOI | Expected value of sample information / value of information (§22) |
| F1 / F2 / F3 | Reconciliation factors. Defaults: F1 = GC model ÷ depleted resource model; F2 = mill received ÷ mine delivered; F3 = F1 × F2. Site definitions differ and are registry rows (§20.4) |
| FA | franken_accounting, the book of record, reached only through the fa --json subprocess (§21) |
| FIFO | Fly-in fly-out rosters such as 14/7 and 8/6 (§19, GB-23) |
| Flip margin | How far an input, or the unmodelled-UU budget, must move before the recommendation changes; a UU form (§9.3) and a field of every DecisionCard (§22) |
| FMT- | A durable binary format with a magic number, version and CRC; formats live in S0 (§26) |
| GEO | Gold-equivalent ounces: other metals converted at a declared, versioned price ratio (§21.6, GB-27) |
| GISTM | Global Industry Standard on Tailings Management: 15 principles, 77 requirements, consequence classes (§18.2) |
| Grade control (GC) | Short-range sampling and modelling that decides ore/waste at the dig face (§16.3, §20) |
| Heap leach | Ore stacked on a lined pad and irrigated with solution; the heap holds an inventory that is a latent state (§17, GB-20) |
| HumanAuthorityToken | The token required to release a prepared effect with safety or legal consequence; agents cannot mint it (§31.3) |
| Indeterminate | The third value of a trigger: evidence is stale, missing or conflicted. It escalates like Triggered (§14.4) |
| KK / KU / UU | Known knowns; known unknowns (KuKind: aleatory, parametric, structural over a hypothesis set); unknown unknowns as an unmodelled budget, never zero (§9) |
| Kriging / OK | Best linear unbiased spatial estimation; ordinary kriging is the usual declared estimator (§13) |
| LabRuntime | asupersync's deterministic virtual-time runtime used for every concurrency test (§26, §33) |
| LGCP / Cox process | Log-Gaussian Cox process: the regional deposit-intensity model, thinned by exploration effort and detectability (§11) |
| LHD | Load-haul-dump underground loader (§16.4) |
| LMDI | Logarithmic mean Divisia index: an exact, order-independent decomposition used for AISC waterfalls (GB-26) |
| LUC | Localised Uniform Conditioning (Abzalov 2006): localizes uniform-conditioning panel distributions to SMUs (§13.1) |
| MCF | Mine call factor: metal accounted for at the plant over metal called by grade control; definitions vary by site (§20.4) |
| Metal stage | MetalStage: in situ, mined, contained, recoverable (with its recovery card), recovered, payable, sold (§25.2) |
| MNPI | Material non-public information (e.g. drill results before release); walled by compiled caveats (§31.1) |
| MOR | Modes-of-reasoning analysis: the neutral case file and evidence ids that the Brenner passes argued from (§0.6) |
| NI 43-101 / JORC / S-K 1300 | Canadian, Australasian and US disclosure codes for mineral resources and reserves (§24) |
| NRV | Net realizable value test for inventory (IAS 2); price basis set per inventory class (§21.5) |
| Obligation (OB-) | A runtime duty with a deadline and an owner (e.g. OB-TARP, OB-SEAL, OB-COMMIT) that must reach a terminal state (§26.7) |
| P754 | AMIRA P754 code of practice for metal accounting (§17.5) |
| PoF / FoS | Probability of failure; factor of safety (§14.2, GB-39) |
| POX | Pressure oxidation (autoclave) pre-treatment of refractory sulphide gold ore (§17) |
| Preg-robbing | Adsorption of dissolved gold onto carbonaceous ore; reported as a percentage from a spike test (§17.3) |
| Projection | A derived, rebuildable view (fsqlite, fgdb, frankensearch). Never an authority (§27.4) |
| Pseudoflow | Hochbaum's max-flow algorithm used for ultimate pit limits; MineFlow is the parity oracle (§15) |
| Reference class | A set of comparable past cases used to set a prior (e.g. capex overruns, GB-32); registered as REFCLASS- rows (§9.3) |
| Refusal | A typed {code, what, fix} outcome instead of a clamped or fabricated number (§8.4) |
| Region (asupersync) | A structured-concurrency scope owning tasks, budgets and obligations; closes cleanly or reports why not (§26) |
| SAA | Sample-average approximation: optimizing over a finite scenario sample, with a stated sampling gap (§15) |
| SMU | Selective mining unit: the smallest volume that can be mined selectively (§13.4) |
| Spork | asupersync's supervision framework (§26) |
| Support | The physical size and shape a value refers to (core interval, block, SMU, panel, stockpile) (§13.4) |
| SX-EW | Solvent extraction and electrowinning of copper cathode (§17) |
| TARP | Trigger action response plan: registered levels, triggers and required responses (§14.4) |
| TCC | Total cash costs (non-GAAP; Barrick definition per its endnotes) (§21.6) |
| TML | Transportable moisture limit for concentrate shipping under the IMSBC Code (§17.6) |
| TSF | Tailings storage facility (§18) |
| Twin of record | The read-only, anchor-pinned operations model that other agents can cite (§16, M6) |
| Walls | MNPI, venture (JV) and residency boundaries compiled into every query (§31) |